๐Ÿ›ข๏ธ Aagvik 5298 41-35 3BX

Oasis Petroleum North America LLC ยท McKenzie County, ND ยท File #34037 ยท Generated 2026-10-02 18:48

API
33-053-08196
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (7)

Tier Signal Date Service Impact
Tier 1 Requested and received a waiver from the tubing/packer requirement (NDAC 43-02-03-21) for the completion period immediately following fracture stimulation.โฐ TIME-SENSITIVE
๐Ÿ“„ SUNDRY NOTICES AND REPORTS ON WELLS - FORM 4 (JUL 27 2018)
Operator secured a regulatory variance to deviate from standard completion safety rules, allowing casing to be exposed during frac and flowback without a packer.
2018-07-25 Completions / Frac
Tier 3 Well was placed on confidential status immediately after completion, with first production on November 5, 2018.โฐ TIME-SENSITIVE
๐Ÿ“„ SUNDRY NOTICES AND REPORTS ON WELLS - FORM 4 (NOV 16 2018)
Operator secured confidential status to withhold initial production data, a strategic move to control market information.
2018-11-15 General Oilfield Services
Tier 3 Well path required active geosteering and an anti-collision maneuver to underpass an existing well (Aagvik 1-35H) with a ~7' TVD buffer.
๐Ÿ“„ SUNBURST CONSULTING Report (Geology Service)
Demonstrates complex pad drilling with wellbore proximity management, requiring real-time interpretation and directional adjustments to avoid collision.
2018-04-18 Directional Drilling
Tier 3 Drilling encountered significant problems requiring a sidetrack due to stuck pipe and failed cement, adding non-productive time.
๐Ÿ“„ SUNBURST CONSULTING Report (Geology Service)
Substantial drilling dysfunction (stuck pipe, lost returns, failed sidetrack attempt) required multiple interventions including wireline, jars, and cementing.
2018-04-10 General Oilfield Services
Tier 3 Amended the bottom hole location and completion style from a cemented shoe to a 'wet shoe' to allow fracking out the shoe, shortening the lateral.
๐Ÿ“„ SUNDRY NOTICES AND REPORTS ON WELLS - FORM 4 (FEB 26 2018)
Significant late-stage change to well design and target endpoint, moving TD 50' closer and switching to a wet shoe completion to enable shoe fracking.
2018-02-22 Completions / Frac
Tier 3 Requested and received a waiver from open hole logging requirements (NDAC 43-02-03-31), substituting cased hole logs and mud log data.
๐Ÿ“„ SUNDRY NOTICES AND REPORTS ON WELLS - FORM 4 (SEP 2017)
Regulatory approval to skip standard open hole logging suite, reducing data acquisition costs and time during drilling.
2017-10-01 Mud / Fluids
Tier 3 Requested and received permission for a 90-day suspension of drilling after setting surface casing, using a smaller rig initially.
๐Ÿ“„ SUNDRY NOTICES AND REPORTS ON WELLS - FORM 4 (SEP 20 2017)
Planned operational pause to use a smaller, cheaper rig for surface hole, indicating a staged, cost-saving drilling strategy.
Unknown Drilling Rigs

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Directional Drilling & Geosteering
The documented anti-collision maneuver and dense pad drilling (intersecting existing well) demonstrate an ongoing, high-skill requirement for precise wellbore placement and real-time geosteering in the area.
Fishing & Remedial Services
The significant stuck pipe event and sidetrack on this well highlight operational risks in the field; vendors specializing in fishing, jarring, and wellbore recovery may see demand on similar wells.
Pressure-Actuated Completion Tools
The switch to a 'wet shoe' completion design requiring pressure-actuated toe sleeves indicates a specific tooling need for future wells where operators plan to frac out the shoe.
Specialized Drilling (Small Rig)