๐Ÿ›ข๏ธ Gathman SWD 1

Devon Energy Williston, LLC ยท Williams County, ND ยท File #39036 ยท Generated 2026-07-08 03:29

API
3310505787
Target Formation
Inyan Kara (Dakota Group)
Confidence
High

๐Ÿ“Š Signals (5)

Tier Signal Date Service Impact
Tier 3 SWD permit renewal filed by Grayson Mill but approved under new operator Devon post-transferโฐ TIME-SENSITIVE
๐Ÿ“„ Sundry forms and approval stamps
Regulatory continuity challenge: permit renewal initiated by Grayson Mill (05/23/2024) but final approval (08/27/2025) granted after operator change to Devon. Shows regulatory lag and transition complexity.
2025-08-27 General Oilfield Services
Tier 3 Large-scale operator change approved - 1,412 wells transferred from Grayson Mill Operating, LLC to Devon Energy Williston, LLC
๐Ÿ“„ Form 15 and cover letter
Transfer of massive asset portfolio (1,412 wells including SWDs) indicates major corporate realignment or acquisition. Creates immediate service contract re-evaluation opportunity across entire Devon Williston position.
2024-12-10 General Oilfield Services
Tier 3 Tank diking variance approved contingent on as-built schematic submission within 30 days of construction completionโฐ TIME-SENSITIVE
๐Ÿ“„ UIC permit stipulations page 2
Non-standard containment requirement with strict 30-day reporting deadline creates compliance urgency. Variance indicates site-specific engineering challenges.
Relative General Oilfield Services
Tier 3 Pressure test requirement (100 psi over permitted max) on injection pipeline between pump and wellhead prior to injectionโฐ TIME-SENSITIVE
๐Ÿ“„ UIC permit stipulations page 1
Specific, non-routine testing protocol exceeding standard requirements. Must be reported via Sundry Notice with detailed specifications.
Relative General Oilfield Services
Tier 3 Operator must contact NDIC Field Inspector Jessica Gilkey prior to location constructionโฐ TIME-SENSITIVE
๐Ÿ“„ UIC permit stipulations page 1
Named inspector requirement creates specific regulatory pathway and personal relationship dependency. Non-compliance halts operations.
Relative General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Regulatory Compliance & Permitting
Operator transition creates immediate need for permit amendments, bonding updates, and regulatory alignment under Devon's systems. UIC permit renewals require ongoing landowner notifications and AOR reviews.
Pressure Testing & Pipeline Integrity
Specific 100 psi overpressure test requirement creates immediate service need upon facility commissioning or modification. Testing must be documented via Sundry Notice with detailed specifications.
Civil Engineering & Surveying
Tank diking variance requires as-built schematic submission within 30 days of construction completion. Ongoing need for survey and engineering services to maintain compliance.
Water Management & Disposal
Large-scale SWD operation (20,000 BWPD capacity) requires continuous water handling services. Transfer may open opportunities for new water midstream contracts under Devon.