| Tier | Signal | Date | Service Impact |
|---|---|---|---|
| Tier 2 |
Operator is using a 'wet shoe' completion design for the production liner with the 'ability to frac out the shoe'. ๐ Stipulations/Conditions of Approval; Completion Program description in Drilling Plan Specific completion technique that influences cementing and stimulation design. Mentioned as a basis for regulatory approval of reduced south setback. |
Unknown | Completions / Frac |
| Tier 3 |
Well is part of a 4-well pad (Stout 16 Pad) developing two separate 1920-acre spacing units, with detailed anti-collision planning against three offset wells on the same pad. ๐ Multi-well references in affidavits, anti-collision report dated March 11, 2026 High-density pad drilling with precise wellbore proximity management. Anti-collision report shows close approaches (Level 3 warnings) with offsets Stout 1604-1BH and Stout 1633-3BH. |
2026-03-11 | Directional Drilling |
| Tier 3 |
Operator requested and received a 1-year APD extension on June 30, 2025, after a previous extension on August 5, 2024.โฐ TIME-SENSITIVE ๐ Sundry Forms for Permit Renewal (Form ID 254190, 197855) Demonstrates persistent intent to drill over multiple years, with active permit maintenance. The well was ultimately spudded in April 2026. |
2025-06-30 | General Oilfield Services |
| Tier 3 |
Operator successfully requested a waiver for open hole logs, relying on offset well data. ๐ Sundry Form ID 127034, dated 07/10/2023 Non-standard regulatory approval reduces logging costs and time. Demonstrates operator's reliance on and confidence in existing subsurface data from offset Quarne #1 well. |
2023-07-10 | Regulatory / Permitting |
| Tier 3 |
Operator requested and received a waiver from the standard 3-day waiting period to commence operations after permit publication.โฐ TIME-SENSITIVE ๐ Affidavit dated June 8, 2023; Permit Review Policy section dated 7/6/2023 Expedites pad construction and drilling start, indicating urgency and coordinated multi-well pad development. Waiver granted based on high working interest ownership (82.8%-97.5%). |
2023-06-08 | Regulatory / Permitting |
| Tier 3 |
Drilling plan specifies a closed mud system with no cuttings pit, and all drill cuttings will be disposed at '13 Mile Landfill, Williston, ND'. ๐ Stipulations section; Drilling Fluids Program note Pre-selected waste disposal facility and mandated closed-loop system. Eliminates onsite cuttings pits. |
Unknown | Mud / Fluids |
| Tier 3 |
APD was modified to upsize surface casing to 13.375", add a Dakota string, and update facility layout. ๐ Permit Information section shows 'Permit Modification' Significant mid-plan design change indicating revised wellbore construction and possibly different geologic or pressure containment needs. Requires different casing, cement, and related services. |
Relative | General Oilfield Services |