| Tier | Signal | Date | Service Impact |
|---|---|---|---|
| Tier 1 |
Variance to NDAC tubing/packer requirement, citing safety factors and monitoring ๐ WELL SUNDRY FORM - Tubing/Packer Waiver Waiver for completion equipment, based on casing strength and monitoring assurances |
2025-01-29 | Regulatory / Permitting |
| Tier 3 |
Waiver requested for collection of drill cutting samples in vertical portion, citing use of samples from adjacent well Borsheim 34-27 6H on the same pad ๐ WELL SUNDRY FORM - Drill Cutting Samples Waiver Non-standard waiver to avoid redundant sampling, potentially reducing costs and time in multi-well pad operations |
2026-01-28 | Regulatory / Permitting |
| Tier 3 |
Request to revise casing and cementing plan, changing surface casing from 13.5" to 17.5" and intermediate from 9.625" to 13.375" ๐ WELL SUNDRY FORM - Request to Revise Casing and/or Cementing Plan Modification to casing design post-permit, suggesting adaptive engineering for specific subsurface conditions or cost optimization |
2025-08-06 | General Oilfield Services |
| Tier 3 |
Waiver for open hole logs, using offset well Orville 4-9 1H logs ๐ WELL SUNDRY FORM - Open Hole Log Waiver Reliance on nearby well data to skip logging, reducing regulatory requirements |
2025-01-30 | Regulatory / Permitting |
| Tier 3 |
Suspension of drilling for up to 90 days to use smaller rig for surface hole before larger rig arrivesโฐ TIME-SENSITIVE ๐ WELL SUNDRY FORM - Suspension of Drilling Phased drilling approach to manage rig availability and costs, deviating from standard continuous drilling |
2025-01-29 | Drilling Rigs |
| Tier 3 |
Waiver for filter sock container during drilling phase, as filtration not used ๐ WELL SUNDRY FORM - Filter Sock Container Waiver Exemption from standard environmental containment, indicating mud system design without filtration |
2025-01-29 | Mud / Fluids |
| Tier 3 |
Backbuild order waiver for wells entering adjacent spacing unit ๐ SUBJECT: Borsheim South Pad - Backbuild Order Waiver Waiver for horizontal wells crossing unit boundaries, citing operator self-notification |
2025-01-02 | Regulatory / Permitting |
| Tier 3 |
H2S mitigation plan with detailed response procedures, fixed detectors, and training requirements ๐ HYDROGEN SULFIDE MITIGATION PLAN Comprehensive H2S contingency for potential sour gas, including ignition procedures and equipment |
2025-01-02 | General Oilfield Services |