๐Ÿ›ข๏ธ HBU MARMON FEDERAL 24X-13F

XTO ENERGY INC ยท Williams County, ND ยท File #41580 ยท Generated 2026-08-21 23:59

API
33-105-06436
Target Formation
Three Forks 1st Bench
Confidence
High

๐Ÿ“Š Signals (7)

Tier Signal Date Service Impact
Tier 2 Operator requested and received waiver from tubing/packer requirement during completion flowback, relying on casing integrity and pressure monitoring.
๐Ÿ“„ Tubing/Packer Waiver Sundry Form (FORM ID: 286021)
Non-standard completion practice that reduces upfront equipment and installation. Indicates confidence in casing design and real-time monitoring, but increases operational risk during flowback.
2025-12-03 Regulatory / Permitting
Tier 3 Operator requested and received suspension of drilling for up to 90 days to use a smaller rig for surface hole, then move off and bring larger rig within 90 days to complete drilling.โฐ TIME-SENSITIVE
๐Ÿ“„ Suspension of Drilling Sundry Form (FORM ID: 239577)
Reveals a staged drilling approach to achieve cost and time savings. Indicates operator is willing to accept regulatory complexity and pad idle time for economic optimization.
2025-04-01 Drilling Rigs
Tier 3 Operator requested and received waiver for open hole logs, relying on offset well HBU Bjarne Federal 34X-13 (File #18078) within a mile for formation tops.
๐Ÿ“„ Open Hole Log Waiver Sundry Form (FORM ID: 230317)
Shows operator is confident in subsurface model from existing data, eliminating a standard data acquisition step to reduce cost and time.
2025-02-11 Regulatory / Permitting
Tier 3 NDIC required a long-term visual monitoring program for pad stability, with specific reporting to field inspector if movement observed, based on Braun Intertec recommendations.
๐Ÿ“„ Permit Conditions of Approval (Page 2 of 10)
Regulatory condition tied to geotechnical concerns on this specific pad due to high cuts/fills. Imposes ongoing monitoring liability on operator.
2025-02-04 General Oilfield Services
Tier 3 BLM notification required for federal minerals within spacing unit, indicating potential additional regulatory layer for this pad.
๐Ÿ“„ BLM Email Correspondence
Reveals federal mineral involvement in Hofflund-Bakken Unit, adding BLM to the regulatory stack for these wells.
2025-01-30 General Oilfield Services
Tier 3 Geotechnical addendum required 100% Proctor compaction within 25 feet of any wellhead in fill areas, with 8-inch maximum lifts and testing on each lift.
๐Ÿ“„ Braun Intertec Addendum 1 to Geotechnical Report
Exceptional earthwork specification due to pad stability concerns. Far exceeds typical compaction standards to ensure wellhead integrity on fill.
2024-05-31 General Oilfield Services
Tier 3 Operator committed to weekly earthwork progress reports from Braun Intertec to NDIC during pad construction due to high visibility and geotechnical complexity.โฐ TIME-SENSITIVE
๐Ÿ“„ Braun Intertec Construction Observation Letter
Regulator-imposed transparency and oversight during construction phase, indicating heightened scrutiny on this pad.
2024-05-31 General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Geotechnical & Earthwork Construction
Pad requires exceptional compaction (100% Proctor near wellheads), benching, moisture conditioning, and weekly reporting. High-spec work needed before drilling.
Surveying & Monitoring
Long-term visual monitoring program mandated by NDIC. Settlement monuments must be established and surveyed monthly/quarterly for years.
Pressure Monitoring & Well Control
Tubing/packer waiver increases reliance on real-time pressure monitoring during completion flowback to detect casing issues.
Directional Drilling & MWD
Complex pad with anti-collision concerns. Multiple vendors (Noble, Gordon) already engaged, but opportunity for alternative providers on future pads.