| Tier | Signal | Date | Service Impact |
|---|---|---|---|
| Tier 2 |
Operator requested and received waiver from tubing/packer requirement during completion flowback, relying on casing integrity and pressure monitoring. ๐ Tubing/Packer Waiver Sundry Form (FORM ID: 286021) Non-standard completion practice that reduces upfront equipment and installation. Indicates confidence in casing design and real-time monitoring, but increases operational risk during flowback. |
2025-12-03 | Regulatory / Permitting |
| Tier 3 |
Operator requested and received suspension of drilling for up to 90 days to use a smaller rig for surface hole, then move off and bring larger rig within 90 days to complete drilling.โฐ TIME-SENSITIVE ๐ Suspension of Drilling Sundry Form (FORM ID: 239577) Reveals a staged drilling approach to achieve cost and time savings. Indicates operator is willing to accept regulatory complexity and pad idle time for economic optimization. |
2025-04-01 | Drilling Rigs |
| Tier 3 |
Operator requested and received waiver for open hole logs, relying on offset well HBU Bjarne Federal 34X-13 (File #18078) within a mile for formation tops. ๐ Open Hole Log Waiver Sundry Form (FORM ID: 230317) Shows operator is confident in subsurface model from existing data, eliminating a standard data acquisition step to reduce cost and time. |
2025-02-11 | Regulatory / Permitting |
| Tier 3 |
NDIC required a long-term visual monitoring program for pad stability, with specific reporting to field inspector if movement observed, based on Braun Intertec recommendations. ๐ Permit Conditions of Approval (Page 2 of 10) Regulatory condition tied to geotechnical concerns on this specific pad due to high cuts/fills. Imposes ongoing monitoring liability on operator. |
2025-02-04 | General Oilfield Services |
| Tier 3 |
BLM notification required for federal minerals within spacing unit, indicating potential additional regulatory layer for this pad. ๐ BLM Email Correspondence Reveals federal mineral involvement in Hofflund-Bakken Unit, adding BLM to the regulatory stack for these wells. |
2025-01-30 | General Oilfield Services |
| Tier 3 |
Geotechnical addendum required 100% Proctor compaction within 25 feet of any wellhead in fill areas, with 8-inch maximum lifts and testing on each lift. ๐ Braun Intertec Addendum 1 to Geotechnical Report Exceptional earthwork specification due to pad stability concerns. Far exceeds typical compaction standards to ensure wellhead integrity on fill. |
2024-05-31 | General Oilfield Services |
| Tier 3 |
Operator committed to weekly earthwork progress reports from Braun Intertec to NDIC during pad construction due to high visibility and geotechnical complexity.โฐ TIME-SENSITIVE ๐ Braun Intertec Construction Observation Letter Regulator-imposed transparency and oversight during construction phase, indicating heightened scrutiny on this pad. |
2024-05-31 | General Oilfield Services |