๐Ÿ›ข๏ธ BW-IDA-LS-149-101-2321H-1

Hess Bakken Investments II, LLC ยท McKenzie County, ND ยท File #41588 ยท Generated 2026-08-22 00:02

API
33-053-10516
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (6)

Tier Signal Date Service Impact
Tier 2 Suspension of Drilling (SOD) request for up to 90 days to use a smaller rig for surface hole only, then move off and bring larger rig later.โฐ TIME-SENSITIVE
๐Ÿ“„ Sundry Form - Request for Consideration/Waiver - Suspension of Drilling
Reveals a staged, cost-saving drilling strategy: spud with a small rig (3-5 days), set surface casing, suspend, then bring Nabors X28 rig within 90 days. Creates two distinct rig mobilization/demobilization events and a window for surface casing services separate from main drilling.
2025-02-25 Drilling Rigs
Tier 2 Use of a 'wet shoe' sub on the 4-1/2" liner with intentional 2 bbl over-displacement to allow fracking out the shoe.
๐Ÿ“„ Drilling Prognosis - Completion Equipment section
Non-standard cementing/completion design. Wet shoe sub with rupture pins allows first frac stage to be pumped out the shoe, enabling closer wellbore placement to section line (150 ft setback).
Unknown Completions / Frac
Tier 3 Lateral drilling encountered Lower Bakken Shale at 23,644' MD, leading to a sidetrack operation.
๐Ÿ“„ Geologic Summary - Lateral section
Unplanned geological event (drilling out of zone) required a sidetrack. Operation involved troughs, time drilling, and slides from 21,251' MD to 21,336' MD. Indicates geo-steering challenges or formation dip changes.
2025-11-23 Directional Drilling
Tier 3 MWD tool failure at 21,763' MD led to trip out of hole (TOOH) and troubleshooting attempts before sidetrack decision.
๐Ÿ“„ Geologic Summary - Lateral section
Tool failure caused non-productive time and preceded the sidetrack operation. Multiple downlink attempts failed, indicating a persistent tool issue, not a communication glitch.
2025-11-20 Drilling Rigs
Tier 3 Mandatory sample collection program dictated by NDIC with specific intervals (30' vertical/curve, 200' lateral) and archiving at Hess Houston and NDGS library.
๐Ÿ“„ NDIC Letter - Cores and Samples
Regulatory mandate overrides operator discretion. Requires specific sampling protocol and dual archiving (operator and state). Creates a fixed workflow for mudlogging/geological services.
2025-02-11 Mud / Fluids
Tier 3 Open hole log waiver granted based on offset well within one mile.
๐Ÿ“„ Sundry Form - Open Hole Log Waiver
Operator avoided routine open hole logging, reducing time and cost. Relies on offset data (STEEN 149-101-13-24-1H) and only ran GR-CBL from TD to surface. Indicates high confidence in subsurface model in this area.
2025-02-06 Regulatory / Permitting

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Drilling Rig Services (Small & Large)
Two-phase rig strategy: immediate need for a small rig for surface hole (as per SOD request), followed by mobilization of Nabors X28 within a 90-day window. Creates sequential opportunities.
Directional Drilling / Geo-steering / MWD
Sidetrack event shows geo-steering challenges in the Middle Bakken lateral. MWD tool failure indicates potential need for more reliable tools or services. High anti-collision risk on pad demands precise surveying and real-time monitoring.
Cementing & Liner Services
Non-standard wet shoe sub design for the 4-1/2" liner requires specialized cementing execution to enable 'frac out the shoe'. Centralizer placement is highly detailed and zone-specific.
Mudlogging & Geological Services
Mandated sample collection at strict intervals (30'/200') creates fixed service scope. Dual archiving requirement (Hess Houston & NDGS) adds logistics complexity.
Civil Construction & Pad Building
Pad is engineered with specific grading, drainage, and facility layout by KLJ Engineering. Construction quantities are detailed (e.g., 27.74 acres disturbance, 131,908 CY excavation).