| Tier 3 |
Suspension of drilling for up to 90 days approved, planning to set surface casing with smaller freshwater-based rig, then mobilize larger rig within 90 days; approximate start date 9/29/2025.โฐ TIME-SENSITIVE ๐ Sundry Form for Well File No.: 41769, Suspension of Drilling Non-standard phased drilling approach to avoid casing wear in vertical/curve sections, prioritizing cost and time savings over continuous operations. |
2025-09-29 | Drilling Rigs |
| Tier 3 |
Waiver of open hole logs requested, citing sufficient logs from offsetting well EN-Will Trust 14-23 (NDIC# 5831), with GR-CBL to be run from TD to ground level. ๐ Sundry Form for Well File No.: 41769, Request for Consideration/Waiver, Type of Work: Open Hole Log Waiver Deviation from standard NDIC Rule 43-02-03-31 requiring open hole logs, indicating cost-saving intent by leveraging existing offset data. |
2025-04-04 | Regulatory / Permitting |
| Tier 3 |
Waiver requested for adjacent unit notification under Order No. 31848 and 31973, as operator owns the adjacent units. ๐ Letter from Derek Abrahamsen dated March 18, 2025 Self-waiver due to intra-company operations, reducing regulatory overhead for multi-unit development. |
2025-03-18 | Regulatory / Permitting |