| Tier | Signal | Date | Service Impact |
|---|---|---|---|
| Tier 2 |
Wet shoe design used on production liner to intentionally over-displace cement by 2 bbls and allow ability to 'frac out the shoe'. ๐ DRILLING PROGNOSIS - Completion Equipment Specific, non-standard cementing/completion design choice to facilitate future stimulation operations by ensuring shoe accessibility. |
Unknown | Completions / Frac |
| Tier 3 |
Pad location was cement-stabilized prior to spud (completed 6/25/2025), with a detailed reclamation plan requiring post-operation soil analysis and potential amendments. ๐ Details of Hess Bakken Investments II, LLC Cement Stabilization Program Non-routine pad construction method indicates investment in pad integrity and pre-planned, analytical final reclamation. Creates a specific future service need for soil milling, testing, and amendment. |
2025-06-25 | General Oilfield Services |
| Tier 3 |
Operator requested and received a 90-day suspension of drilling after surface casing to allow cost/time savings by using a smaller rig for surface hole and a larger rig later.โฐ TIME-SENSITIVE ๐ WELL SUNDRY FORM - Suspension of Drilling Reveals a deliberate operational staging strategy to optimize rig utilization and capital efficiency. This creates a defined window for the larger rig move-in and drilling services. |
2025-04-08 | Directional Drilling |
| Tier 3 |
Operator requested and received a waiver for open-hole logs, relying on offset well GO-JOHN-156-98-0508H-3 logs instead. ๐ WELL SUNDRY FORM - Request for Consideration/Waiver Indicates a cost-saving or operational streamlining decision, reducing wireline/logging scope. Shows reliance on and confidence in specific offset data. |
2025-04-08 | Mud / Fluids |
| Tier 3 |
Five target changes were made throughout the lateral section during drilling. ๐ GEOLOGIC SUMMARY - Lateral section Indicates active, complex geosteering to remain in zone, suggesting geological heterogeneity or operational challenges. |
Relative | Directional Drilling |
| Tier 3 |
Initial landing target was raised from 10,810' TVD to 10,804' TVD due to markers coming in high. ๐ GEOLOGIC SUMMARY - Curve section Shows real-time adaptation of drilling plan based on actual formation encounters, indicating proactive geological oversight. |
Relative | General Oilfield Services |