๐Ÿ›ข๏ธ GO-Ray- 157-97-3321H-5

HESS BAKKEN INVESTMENTS II, LLC ยท Williams County, ND ยท File #41896 ยท Generated 2026-08-22 00:11

API
3310506560
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (6)

Tier Signal Date Service Impact
Tier 2 Permit includes a unique 'Bakken Setback Summary Statement': The north setback is based on a production liner cemented in the lateral with a wet shoe and the ability to frac out the shoe.
๐Ÿ“„ Permit Information - Stipulations
Reveals a specific, pre-approved completion design element (cemented liner with wet shoe) that directly influences well placement and regulatory approval. It's a condition tied to the spacing exception.
2025-05-08 Completions / Frac
Tier 3 NDIC mandates specific, non-standard sample collection protocol: cuttings from Base of Last Charles Salt, at 30' max intervals in vertical/build, 200' max in lateral. Requires washing, drying, specific packaging, and shipment to state library within 30 days of drilling completion.
๐Ÿ“„ Letter from State Geologist - Cores and Samples
Imposes a detailed, prescriptive sample handling workflow that is more stringent than routine. Creates a compliance-driven service requirement with a firm 30-day deadline post-drilling.
2025-05-12 General Oilfield Services
Tier 3 Operator requests and is approved for a waiver of open hole logs, relying on offset well HODENFIELD 15-33H (NDIC# 19130) within a mile. Only a GR-CBL will be run from TD to ground level.
๐Ÿ“„ Sundry Form - Open Hole Log Waiver
Eliminates standard open hole logging suite. Reduces vendor opportunity for logging-while-drilling (LWD) and wireline services on this well, shifting focus to cased hole evaluation.
2025-05-09 Regulatory / Permitting
Tier 3 Approval stipulates a 'closed mud system with no cuttings pit'. Cuttings will be hauled to a state-approved facility.
๐Ÿ“„ Permit Information - Stipulations
Mandates a specific waste management approach, eliminating the option for an on-site cuttings pit. Requires pre-arranged hauling and disposal services.
2025-05-08 Mud / Fluids
Tier 3 Operator requests suspension of drilling for up to 90 days to use a smaller rig for surface hole only, then move off and bring larger rig within 90 days to complete well. Explicitly states intent is for cost and time savings.โฐ TIME-SENSITIVE
๐Ÿ“„ Sundry Form - Request for Consideration/Waiver - Suspension of Drilling
Reveals a staged, cost-optimized drilling strategy using two different rigs. Creates a tight, 90-day window for the larger rig mobilization and completion drilling after surface casing is set.
Relative Drilling Rigs
Tier 3 Hess must contact NDIC Field Inspector Robert Stafford prior to location construction. Also must call immediately after spudding and when plug is bumped with casing/cement info, and when conventional rig moves back on.
๐Ÿ“„ Permit Information - Stipulations & Reviewer Comments
Imposes multiple, specific regulatory touchpoints with a named inspector. Creates a sequence of mandatory notifications that dictate operational pacing and oversight.
Relative Drilling Rigs

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Drilling Rig Services (Large Rotary Rig)
A rig capable of drilling to TD must be mobilized and complete drilling within a 90-day window after the small rig spuds (approx. start 9/24/2025). This is a time-sensitive, high-value slot.
Waste Hauling & Disposal
The 'closed mud system with no cuttings pit' stipulation requires immediate planning for continuous cuttings hauling from spud to TD. A state-approved disposal facility must be lined up.
Cuttings Sample Handling & Logistics
The mandated sample collection protocol creates a need for specialized on-site sample processing (washing, drying), packaging, and shipment to the state core library within 30 days of drilling completion.
Cementing Services
Complex cementing program with specific centralizer placement rules, a cemented production liner, and a 'wet shoe' design for the liner shoe. Requires precise execution to meet plan and regulatory conditions.
Regulatory & Inspection Coordination
Multiple mandatory notifications to a named NDIC field inspector (Robert Stafford) at specific operational milestones (pre-construction, post-spud, plug bump, rig move-on) require careful operational planning and communication.