๐Ÿ›ข๏ธ GO-RAY-157-97-3321H-4

Hess Bakken Investments II, LLC ยท Williams County, ND ยท File #41897 ยท Generated 2026-08-22 00:13

API
3310506561
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (6)

Tier Signal Date Service Impact
Tier 3 Operator requested and received approval for suspension of drilling operations for up to 90 days to use a smaller rig for surface hole only, then move off and bring larger rig within 90 days.โฐ TIME-SENSITIVE
๐Ÿ“„ WELL SUNDRY FORM - Request for Consideration/Waiver
Reveals a staged drilling approach to achieve cost and time savings. Creates two distinct rig move/rig up opportunities: one for a small surface rig (3-5 day window) and another for the main drilling rig (within 90 days of spud).
2025-05-12 Drilling Rigs
Tier 3 NDIC mandated specific sample collection protocol starting at Base of Last Charles Salt, with 30' intervals in vertical/curve and 200' intervals in lateral.
๐Ÿ“„ Letter from ND Geological Survey - CORES AND SAMPLES
Regulatory-driven, non-standard sample collection depth and interval specification. Requires precise compliance from mudlogging contractor.
2025-05-12 Mud / Fluids
Tier 3 Operator requested and received approval to waive open hole logging requirements, citing offset well data within a mile.
๐Ÿ“„ WELL SUNDRY FORM - Open Hole Log Waiver
Avoids routine wireline logging services. Indicates high confidence in offset geology and reliance on mudlogging/XRF for formation evaluation.
2025-05-09 Mud / Fluids
Tier 3 Permit stipulation: 'Surface holes are not to be intentionally deviated' due to potential for severe casing wear.
๐Ÿ“„ PERMIT INFORMATION - Conditions of Approval & SUNDRY FORM Reviewer Comments
Explicit regulatory/engineering constraint on well design. Deviates from common practice where slight surface deviation might be used for pad optimization.
2025-05-08 Directional Drilling
Tier 3 Cemented liner designed with a 'wet shoe' to intentionally over-displace cement by 2 bbls, allowing ability to frac out the shoe.
๐Ÿ“„ DRILLING PROGNOSIS - Completion Equipment
Non-standard cementing design for the production liner. The wet shoe sub with rupture pins is a specific technology choice to facilitate future frac operations.
Unknown Completions / Frac
Tier 3 Lateral section required four target changes while drilling, indicating active geosteering adjustments.
๐Ÿ“„ GEOLOGIC SUMMARY - Lateral section
Higher-than-typical number of target changes suggests geological complexity or active avoidance strategy (e.g., anti-collision, formation changes).
Relative Directional Drilling

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Small Rig / Rat Hole Machine Services
Hess plans to use a smaller rig to drill surface hole only within a 3-5 day window starting ~9/24/2025. Immediate opportunity for rig mobilization, cementing, and move-off services.
Large Rig Mobilization & Services
Primary drilling rig (Nabors X27) required to be on location within 90 days of the surface hole spud (~by late Dec 2025). This is the main drilling phase opportunity.
Mudlogging & Advanced Geochemical Analysis
Neset contracted with specific XRF analysis and sample collection protocol mandated by NDIC. Services are critical due to open hole log waiver.
Cementing & Liner Hardware
Specific 'wet shoe' sub technology required for production liner. Cementing design includes intentional over-displacement for future frac access.
Post-Drilling Sample Handling & Shipping
Regulatory requirement to ship two sets of samples to Hess Houston and ND Geological Survey within 30 days of drilling completion (by ~12/31/2025).