๐Ÿ›ข๏ธ GO-Barb- 157-97-3523H-4

HESS BAKKEN INVESTMENTS II, LLC ยท Williams County, ND ยท File #41902 ยท Generated 2026-08-22 00:15

API
3310506563
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (5)

Tier Signal Date Service Impact
Tier 2 Operator requested and received approval for suspension of drilling operations for up to 90 days after spudding surface hole with a smaller rig, with intent to bring larger rig later to complete well.โฐ TIME-SENSITIVE
๐Ÿ“„ Suspension of Drilling Sundry Form (FORM ID: 247096)
Reveals a staged drilling approach to achieve cost and time savings. Creates a 90-day window between surface casing and full-depth drilling, impacting rig scheduling and service timing.
Relative Drilling Rigs
Tier 3 Approved spud date is in the future (9/29/2025), with detailed cementing report submitted showing adjusted depths for 'big rig' and volumes received vs. calculated.โฐ TIME-SENSITIVE
๐Ÿ“„ Notification of Work Performed - Spud Date Sundry Form
Well file contains a future spud date and associated operational details, indicating advanced planning and regulatory filing for work not yet performed. Cement report shows field adjustments.
2025-09-29 Drilling Rigs
Tier 3 Operator is required to collect and submit drill cuttings samples starting at the Base of the Last Charles Salt at specified intervals, and any cores, within strict timelines (30 days for samples, 180 days for cores).โฐ TIME-SENSITIVE
๐Ÿ“„ Letter from ND Geological Survey regarding Cores and Samples
Non-routine, prescriptive sample collection mandate with defined start point and submission deadlines. Indicates regulatory or geologic interest in specific formations.
2025-05-19 General Oilfield Services
Tier 3 Operator requested and received waiver for open hole logs, relying on offset well HICKEL 15-35H (NDIC# 19066) within a mile, and will only run GR-CBL from TD to surface.
๐Ÿ“„ Request for Consideration/Waiver - Open Hole Log Waiver (FORM ID: 247104)
Indicates a deviation from standard data acquisition, reducing logging scope. Shows reliance on existing subsurface data from a specific offset, suggesting confidence in the area's geologic predictability.
2025-05-13 Regulatory / Permitting
Tier 3 Surface hole is not to be intentionally deviated due to risk of severe casing wear during drilling of vertical and curve sections.
๐Ÿ“„ Suspension of Drilling Sundry Form and Permit Stipulations
Explicit operational constraint driven by casing wear concerns, not a routine regulatory requirement. Indicates specific geomechanical or historical challenges in the area.
Unknown Directional Drilling

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Pad Construction & Civil Earthwork
Detailed engineered pad design with extensive quantities (22,278 CY excavation, 987 LF access road) is approved. Construction must precede spud date of 9/29/2025.
Rig Mobilization/Demobilization & Specialized Drilling Services
Two-phase rig schedule: initial small rig for surface hole (implicit), then larger rig (potentially NaborsX28 per drilling prognosis) within 90 days post-spud. Requires precise timing and possibly different rig contractors.
Cementing & Casing Centralization
Detailed centralizer placement schedules for surface, production, and liner casing indicate specific, non-standard centralization requirements, especially through salt zones.
Sample Collection & Logistics
Mandatory sample collection from Base of Last Charles Salt with 30-day submission deadline post-drilling. Requires on-site sample handling and shipping coordination.
Directional Drilling & Surveying