| Tier | Signal | Date | Service Impact |
|---|---|---|---|
| Tier 1 |
Operator requested and received a variance from tubing/packer requirements, providing detailed engineering assurances based on new high-grade casing, safety factors, and monitoring plans. ๐ WELL SUNDRY FORM - Tubing/Packer Waiver Shows a deliberate design choice to omit standard tubing and packer, backed by a rigorous engineering justification. This alters the standard completion architecture. |
2025-12-09 | Drilling Rigs |
| Tier 2 |
Operator requested and received approval for a 90-day suspension of drilling after setting surface casing with a small rig (Noble #1), planning to return with a larger rig to TD within that window to achieve cost and time savings.โฐ TIME-SENSITIVE ๐ WELL SUNDRY FORM - Suspension of Drilling Reveals a staged drilling strategy: use a smaller, cheaper rig for surface hole, then mobilize a larger capability rig later. Creates a defined 90-day window for the larger rig mobilization and work. |
2025-12-09 | Drilling Rigs |
| Tier 2 |
The permit includes a unique 'Bakken Setback Summary Statement' explaining the east setback is based on a production liner cemented in the lateral with a wet shoe and the 'ability to frac out the shoe'. ๐ PERMIT INFORMATION - Stipulations Explicitly ties the well's legal spacing compliance to a specific completion design feature (cemented liner with wet shoe). This is a direct link between regulatory approval and engineered completion method. |
Unknown | Completions / Frac |
| Tier 3 |
Operator requested and received waiver for open hole logs, relying on offset well data within a mile (Owan Trust South 32-33-34F 4H, NDIC #41949) and committing to run only GR-CBL from TD to ground level. ๐ WELL SUNDRY FORM - Request for Consideration/Waiver (Open Hole Log Waiver) Indicates a deliberate cost/operational efficiency choice to forgo standard open hole logging, relying on nearby well control. This reduces logging service opportunity but may signal a mature area confidence. |
2026-01-27 | Regulatory / Permitting |
| Tier 3 |
Operator requested and received a waiver for the filter sock container requirement for the drilling phase, asserting they do not use filter media during drilling. ๐ WELL SUNDRY FORM - Filter Sock Container Waiver Devon explicitly states they do not use filtration systems during drilling. This is a non-standard operational choice that avoids the need for specific waste handling equipment on site. |
2025-12-09 | Regulatory / Permitting |
| Tier 3 |
Actual spud date (Dec 5, 2025 with Noble #1 rig) was 22 days earlier than the spud date listed in the well summary (Dec 27, 2025). The well summary appears to reference the spud of the main lateral section. ๐ WELL SUNDRY FORM - Notification of Work Performed (Spud Date) vs. WELL SUMMARY Highlights the two-phase drilling operation: initial spud for surface hole, then a later 'spud' for the lateral. This clarifies the actual timeline and the use of two different rigs/operations. |
2025-12-05 | Drilling Rigs |
| Tier 3 |
NDIC stipulation requires Devon to contact Field Inspector Jessica Gilkey prior to location construction, indicating specific regulatory oversight for this pad. ๐ PERMIT INFORMATION - Conditions of Approval A pre-construction notification requirement to a specific inspector suggests heightened regulatory attention or site-specific concerns (e.g., location sensitivity, landowner issues). |
Unknown | General Oilfield Services |