| Tier | Signal | Date | Service Impact |
|---|---|---|---|
| Tier 2 |
Operator requested and received waiver to run tubing and packer, planning to flow well up 7'' casing after frac completion ๐ WELL SUNDRY FORM - Request for Consideration/Waiver Deviates from standard completion design; indicates intent to flow back up casing rather than tubing, which requires regulatory approval and specific safety monitoring commitments |
2026-07-20 | Completions / Frac |
| Tier 3 |
Curve section short-landed at 9,584' MD due to lost circulation, casing set near top of Middle Bakken rather than deeper in target ๐ GEOLOGIC SUMMARY Operational problem forced compromise on casing point; may affect lateral placement and completion effectiveness |
2025-11-16 | General Oilfield Services |
| Tier 3 |
Operator requested and approved Suspension of Drilling (SOD) for up to 90 days after spudding with small rig, planning to move larger rig on location laterโฐ TIME-SENSITIVE ๐ WELL SUNDRY FORM - Suspension of Drilling Unusual two-rig strategy: spud with T&S Drilling Rig #2, then bring Nabors B21 later. Indicates pad optimization or rig availability constraints |
2025-08-01 | Drilling Rigs |
| Tier 3 |
Operator certified they will not use diesel fuel in hydraulic fracture stimulation operations ๐ Statement Regarding Hydraulic Fracture Stimulation using Diesel Fuel Formal regulatory commitment affecting frac fluid design; indicates environmental compliance focus |
2025-04-01 | Completions / Frac |
| Tier 3 |
Lateral section drilled with produced water as drilling fluid instead of oil-based mud ๐ GEOLOGIC SUMMARY Non-standard fluid program: vertical/curve used BaraXcel (oil-based), lateral used produced water. Indicates cost-saving or environmental strategy |
Relative | Mud / Fluids |