| Tier | Signal | Date | Service Impact |
|---|---|---|---|
| Tier 3 |
KLX Directional Drilling survey certification report dated 26 December 2025, with sidetrack information blank. ๐ KLX Survey Certification Report Post-spud survey completion, confirming directional path without sidetrack. |
2025-12-26 | Directional Drilling |
| Tier 3 |
Waiver requested for open hole logs, citing offsetting well Amber 2104-5BH (NDIC File #42236) within 1 mile, with GR-CBL to be run from TD to ground level. ๐ Sundry Form for Well File No.: 41975 (FORM ID: 281956) Duplicate waiver request, possibly indicating initial submission issues or updated justification. |
2025-11-12 | Regulatory / Permitting |
| Tier 3 |
Spudded well on 10/12/2025 with Stoneham #17 rig.โฐ TIME-SENSITIVE ๐ Sundry Form for Well File No.: 41975 (Notification of Work Performed) Actual start of drilling operations. |
2025-10-12 | Drilling Rigs |
| Tier 3 |
Waiver requested for open hole logs, citing offsetting wells Amber 2104-5BH (NDIC File #42236) and Amber 2133-14BH (NDIC File #41974) within 1 mile for formation tops establishment, with GR-CBL to be run from TD to ground level. ๐ Sundry Form for Well File No.: 41975 (FORM ID: 255283) Non-standard waiver for open hole logs, relying on adjacent wells, potentially reducing costs and time for logging operations. |
2025-06-24 | Regulatory / Permitting |
| Tier 3 |
Waiver approved for three-day waiting period prior to construction/operations, with operator holding 94.32% working interest in DSU.โฐ TIME-SENSITIVE ๐ AFFIDAVIT REQUEST FOR WAIVER TO THREE-DAY WAITING PERIOD (FORM ID #235652 and #235485) Accelerated timeline for pad development, bypassing standard waiting period. |
2025-03-12 | Regulatory / Permitting |
| Tier 3 |
Mud motor stalled and bit hung up at 7,386' MD, requiring work free with torque and circulation adjustments. ๐ Drilling Operations log Unexpected drilling difficulty in vertical section, leading to operational adjustments. |
Relative | Mud / Fluids |
| Tier 3 |
Encountered tight spots and pack-offs during lateral drilling, with lost returns up to 80-90 BBLS, mitigated by mud weight increases to 10.5 PPG and additives like GILSONITE and MOUNTAIN PLEX. ๐ Drilling Operations log Frequent wellbore stability issues requiring LCM pills and mud adjustments. |
Relative | Mud / Fluids |