๐Ÿ›ข๏ธ DROVDAL 5-8 3H

DEVON ENERGY WILLISTON, L.L.C ยท McKenzie County, ND ยท File #41987 ยท Generated 2026-08-22 00:27

API
3305310595
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (9)

Tier Signal Date Service Impact
Tier 1 Operator requested and received variance from tubing/packer requirement (NDAC 43-02-03-21) with detailed engineering assurances, including use of new high-burst casing, safety factor of 0.85, and specific monitoring/flowback procedures.
๐Ÿ“„ Sundry Form - Tubing/Packer Waiver
Signals a deliberate design choice to omit tubing/packer, backed by engineered safety case; indicates potential cost/time savings but requires strict adherence to stated procedures.
2025-09-12 General Oilfield Services
Tier 3 Operator requested and received waiver for drill cutting samples in vertical portion (Base of Last Salt to curve KOP), citing samples already collected from offset well Drovdal 5-8 XE 1H on same pad.
๐Ÿ“„ Sundry Form - Request for Consideration/Waiver (Drill Cutting Samples Waiver)
Indicates pad-level sampling strategy to reduce redundancy; signals operational efficiency focus and potential reduction in mud logging/sample handling scope for vertical sections on multi-well pads.
2026-01-27 Mud / Fluids
Tier 3 Spud notification confirms use of Nabors B13 rig.
๐Ÿ“„ Sundry Form - Notification of Work Performed (Spud Date)
Identifies specific drilling contractor and rig number, revealing active equipment deployment.
2026-01-10 Drilling Rigs
Tier 3 Operator requested and received open hole log waiver, citing offset well Loomer State 150-99-5-8-2H (File #24526) within a mile as sufficient for formation tops; will run GR-CBL from TD to ground level instead.
๐Ÿ“„ Sundry Form - Open Hole Log Waiver
Eliminates standard open hole logging run, substituting with cased hole logs; indicates reliance on offset data and reduces logging time/cost.
2025-09-12 Regulatory / Permitting
Tier 3 Operator requested and received waiver for filter sock container requirement, stating they do not use filter media during drilling.
๐Ÿ“„ Sundry Form - Filter Sock Container Waiver
Non-standard exemption from regulatory container mandate; indicates unique drilling fluid/filtration practice that eliminates need for on-site filter waste handling.
2025-09-12 Regulatory / Permitting
Tier 3 Permit includes stipulation for deep surface casing (13-3/8") not penetrating Mowry Formation, requiring mud logger from ground level to TD of surface hole at โ‰ค30' intervals, and no intentional deviation in surface hole.
๐Ÿ“„ Permit Stipulations (Page 2)
Unusual regulatory mandate for mud logging starting at surface (typically deeper); constrains directional control in surface hole, indicating geohazard or groundwater protection focus.
2025-06-10 Directional Drilling
Tier 3 Permit requires CBL on 13-3/8" surface casing, 9-5/8" intermediate, and 7" casing, with specific instructions for zero-pressure pass and waiting on cement for sufficient compressive strength.
๐Ÿ“„ Permit Stipulations (Page 2-3)
Enhanced cement verification protocol across multiple casing strings, indicating regulatory or operator focus on zonal isolation integrity.
2025-06-10 General Oilfield Services
Tier 3 Surface owner notification affidavit shows Devon notified XTO Energy Inc. as adjacent spacing unit operator per NDIC Order 31848, providing directional plans, approximate start date, and contact info.
๐Ÿ“„ State of North Dakota County of Williams affidavit
Reveals regulatory-mandated engagement with specific competitor (XTO) regarding wellbore entry into adjacent unit; indicates potential coordination or conflict management.
2025-04-15 Directional Drilling
Tier 3 Drilling plan specifies closed loop system with cuttings hauled to Ideal Oilfield Disposal, LLC at a specific address in Arnegard, ND.
๐Ÿ“„ Proposed Drilling Plan - Disposal of Drill Cuttings
Explicitly names waste disposal vendor and location, indicating pre-selected contractor and waste handling logistics.
Unknown General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Cased Hole Logging (GR-CBL)
Required on surface, intermediate, and production casing strings per permit; open hole log waiver increases reliance on cased hole data. Timing aligns with casing runs post-spud.
Mud Logging
Mandated from ground level to TD of surface hole at โ‰ค30' intervals due to deep surface casing stipulation. Immediate need upon spud.
Cementing & CBL Coordination
Multiple CBL requirements with specific WOC times; cementing contractors must ensure blends achieve compressive strength before logging runs to avoid delays.
Directional Drilling & Surveying
No deviation allowed in surface hole; survey frequency requirements (100' vertical, 30' curve, 90' lateral) must be met. Curve and lateral drilling imminent post-surface casing.
Waste Hauling (Drill Cuttings)
Closed-loop system with cuttings hauled to Ideal Oilfield Disposal; continuous service needed during drilling operations.