๐Ÿ›ข๏ธ LOOMER 11-2 6H

DEVON ENERGY WILLISTON, L.L.C ยท McKenzie County, ND ยท File #42172 ยท Generated 2026-09-15 03:32

API
3305310645
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (5)

Tier Signal Date Service Impact
Tier 2 Permit stipulates that due to location on an aquifer and within Watford City's Extra-Territorial Jurisdiction, an onsite inspection is required prior to construction, with specific stipulations including a closed mud system, no drilling pit, and impermeable liner.
๐Ÿ“„ Permit Information, Page 2 of 11
Imposes stringent, non-routine location construction requirements triggered by sensitive siting, requiring pre-approval from a specific field inspector.
2026-01-14 Mud / Fluids
Tier 2 Operator requested and received a waiver from the tubing/packer requirement (NDAC 43-02-03-21) for flowback, citing high-spec casing and monitoring.
๐Ÿ“„ Sundry Form (Request for Consideration/Waiver), FORM ID: 262825
Non-standard completion design choice that deviates from typical regulatory casing/tubing rules, based on engineered safety assurances.
2025-08-11 Regulatory / Permitting
Tier 2 Operator requested and received approval for a 90-day suspension of drilling to use a smaller rig for surface hole only, with a larger rig to return within 90 days.โฐ TIME-SENSITIVE
๐Ÿ“„ Sundry Form (Suspension of Drilling), FORM ID: 262821
Indicates a staged, cost-saving drilling approach with a defined, short-term window for the main drilling rig to mobilize.
2025-08-08 Drilling Rigs
Tier 3 Operator proactively submitted a Best Management Practices letter detailing pad design, stormwater management, SCADA, spill response, and drilling waste disposal contractor.
๐Ÿ“„ Wehrung West BMP Letter
Unusually detailed, voluntary disclosure of operational plans and pre-selected vendors to address regulatory concerns over aquifer and extraterritorial jurisdiction.
2025-07-23 General Oilfield Services
Tier 3 Operator's 'Proposed Work' section states intent to retain flexibility to add a Dakota intermediate casing string if needed, citing elevated pressure experience on an adjacent pad.
๐Ÿ“„ Proposed Work, Page 8 of 11
Explicitly plans for a contingent intermediate casing string based on offset well pressure problems, indicating anticipated downhole challenges.
Unknown General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Drilling Rig Services
A large drilling rig is contractually needed to move onto location within 90 days of the surface hole spud (which occurred on 5/3/26) to complete the well, per the approved suspension of drilling.
Location Construction & Environmental Controls
Stringent stipulations for closed mud systems, impermeable liners, and berms are in effect due to the aquifer and ETJ location, requiring immediate action before further work.
Casing & Cementing Services
Operator has explicitly planned for the possible need to run a contingent Dakota intermediate casing string, creating potential additional work scope.
Waste Hauling & Disposal
Operator has declared use of specific landfills (WISCO, Select Water Solutions) for drill cuttings, indicating active waste handling contracts.