๐Ÿ›ข๏ธ LOOMER 11-2 7H

DEVON ENERGY WILLISTON, L.L.C ยท McKenzie County, ND ยท File #42173 ยท Generated 2026-09-02 04:25

API
3305310646
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (7)

Tier Signal Date Service Impact
Tier 2 Operator requested and received suspension of drilling (SOD) for up to 90 days to use smaller rig for surface hole only, then return with larger rig to TD.โฐ TIME-SENSITIVE
๐Ÿ“„ Suspension of Drilling Sundry (FORM ID: 262822)
Non-standard drilling sequence to achieve cost savings. Requires coordination between two different rig contractors and creates a 90-day window for larger rig mobilization.
2025-08-08 Drilling Rigs
Tier 2 Multiple regulatory waivers approved: tubing/packer requirement, filter sock container for drilling phase, and open hole logs.
๐Ÿ“„ Various Sundry Forms (262828, 262819, 262811)
Operator successfully obtained multiple regulatory concessions, indicating established relationship with NDIC and confidence in alternative compliance methods.
2025-08-07 to 2025-08-11 Regulatory / Permitting
Tier 2 Design includes 'wet shoe with ability to frac out the toe' and backup hyd toe sleeve in case wet shoe fails, plus ball seat for testing liner.
๐Ÿ“„ Proposed Work and Section Details
Unusual completion design with redundant systems for toe initiation. Wet shoe approach differs from standard plug-and-perf.
Unknown Completions / Frac
Tier 3 Pad located within Watford City's Extra-Territorial Jurisdiction AND on an aquifer, triggering extensive site-specific stipulations including closed mud system, impermeable liner, H2S plan, fencing, perimeter berm, and special casing requirements.
๐Ÿ“„ Permit stipulations pages 2-3
Dual regulatory triggers (municipal jurisdiction + aquifer) create complex compliance requirements that exceed standard Bakken well specs.
2026-01-14 Mud / Fluids
Tier 3 Operator proactively conducted geotech and depth-to-groundwater analysis for pad expansion over aquifer and communicated with Watford City planner prior to permit submission.
๐Ÿ“„ Wehrung Pad BMP Letter (July 22-23, 2025)
Shows proactive regulatory engagement and pre-permit stakeholder management. Operator invested in site characterization before formal application.
2025-07-23 General Oilfield Services
Tier 3 Verbal approval granted for MWD failure contingency - allowed to drill blind from survey at 21348' MD an additional 347' with specific risk warning to stop a joint of pipe before the limit.
๐Ÿ“„ INSPECTOR COMMENTS section
Regulatory exception for equipment failure shows operational flexibility and risk tolerance. Inspector explicitly states operator proceeds at own risk, indicating potential geosteering or survey challenges.
Unknown General Oilfield Services
Tier 3 Operator requested flexibility to add Dakota string 'if/when needed' citing elevated Dakota pressure experienced on adjacent SKAAR pad.
๐Ÿ“„ PROPOSED WORK section
Contingency planning based on offset well experience shows anticipation of potential pressure problems. Design allows for mid-operation modification.
Unknown General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Environmental & Containment Services
Aquifer location + municipal jurisdiction requires closed mud systems, impermeable liners, specialized berms, moats, and spillways. Immediate need for compliant construction.
Drilling Rig Services (Phased)
90-day window between surface hole drilling (small rig) and TD drilling (large rig). Two separate contracting opportunities with specific timing requirements.
Pressure Control & Casing Services
Potential Dakota string addition based on offset pressure experience. Deep surface casing (13-3/8" @ 4100') with strict cement bond log requirements.
Surveying & Geosteering
MWD failure contingency approved for blind drilling. Complex trajectory with specific setback requirements (150' N/S, 500' E/W).