| Tier | Signal | Date | Service Impact |
|---|---|---|---|
| Tier 1 |
Operator proactively requested and received multiple regulatory waivers (tubing/packer, filter sock container for drilling phase, open hole logs) prior to spud. ๐ Multiple Sundry Forms (FORM IDs: 262830, 262820, 262815) Demonstrates advanced regulatory planning and effort to streamline operations by removing non-essential requirements based on design and offset data. |
2025-08-07 | Regulatory / Permitting |
| Tier 3 |
Operator requested and received a 90-day suspension of drilling after spudding surface hole with a smaller rig, intending to return with a larger rig to complete drilling.โฐ TIME-SENSITIVE ๐ Sundry Form (Suspension of Drilling) - FORM ID: 262823 Reveals a staged, cost-saving drilling strategy. Creates a defined 90-day window for the larger drilling rig and associated services to mobilize. |
2025-08-08 | Drilling Rigs |
| Tier 3 |
Operator submitted a detailed Best Management Practices (BMP) letter to NDIC outlining planned measures for aquifer protection, stormwater, spill response, SCADA/alarms, and midstream coordination. ๐ Wehrung West BMP Letter (July 22-23, 2025) Proactive, voluntary disclosure of high-standard operational plans to address regulatory concerns, indicating a high level of planning and investment in surface management. |
2025-07-23 | General Oilfield Services |
| Tier 3 |
Operator explicitly states intent to potentially add a Dakota casing string due to increased SWD activity and elevated pressures experienced on an adjacent pad (SKAAR pad). ๐ PROPOSED WORK section (Page 8 of 12) Reveals contingency planning based on direct, recent operational experience with subsurface pressure issues in the immediate area. |
2025-01-14 | General Oilfield Services |
| Tier 3 |
Well is located within Watford City's Extra-Territorial Jurisdiction and on an aquifer, triggering extensive, non-routine location construction stipulations (closed mud system, no pit, impermeable liner, perimeter berm, etc.). ๐ Permit Stipulations (Page 2 of 12) Location construction is highly regulated and engineered beyond standard pads, requiring specific materials and methods. |
2025-01-14 | Mud / Fluids |
| Tier 3 |
Permit stipulation requires contact with specific NDIC Field Inspector (Marc Binns) prior to location construction and for onsite inspection due to aquifer and ETJ location. ๐ Permit Stipulations (Page 2 of 12) Creates a mandatory regulatory checkpoint before dirt work begins. Inspector may add site-specific stipulations on arrival. |
2025-01-14 | General Oilfield Services |