โ† Back to Daily Permits

๐Ÿ›ข๏ธ LOOMER 11-2 8H

DEVON ENERGY WILLISTON, L.L.C ยท McKenzie County, ND ยท File #42174 ยท Generated 2026-08-26 06:25

API
3305310647
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (6)

Tier Signal Date Service Impact
Tier 1 Operator proactively requested and received multiple regulatory waivers (tubing/packer, filter sock container for drilling phase, open hole logs) prior to spud.
๐Ÿ“„ Multiple Sundry Forms (FORM IDs: 262830, 262820, 262815)
Demonstrates advanced regulatory planning and effort to streamline operations by removing non-essential requirements based on design and offset data.
2025-08-07 Regulatory / Permitting
Tier 3 Operator requested and received a 90-day suspension of drilling after spudding surface hole with a smaller rig, intending to return with a larger rig to complete drilling.โฐ TIME-SENSITIVE
๐Ÿ“„ Sundry Form (Suspension of Drilling) - FORM ID: 262823
Reveals a staged, cost-saving drilling strategy. Creates a defined 90-day window for the larger drilling rig and associated services to mobilize.
2025-08-08 Drilling Rigs
Tier 3 Operator submitted a detailed Best Management Practices (BMP) letter to NDIC outlining planned measures for aquifer protection, stormwater, spill response, SCADA/alarms, and midstream coordination.
๐Ÿ“„ Wehrung West BMP Letter (July 22-23, 2025)
Proactive, voluntary disclosure of high-standard operational plans to address regulatory concerns, indicating a high level of planning and investment in surface management.
2025-07-23 General Oilfield Services
Tier 3 Operator explicitly states intent to potentially add a Dakota casing string due to increased SWD activity and elevated pressures experienced on an adjacent pad (SKAAR pad).
๐Ÿ“„ PROPOSED WORK section (Page 8 of 12)
Reveals contingency planning based on direct, recent operational experience with subsurface pressure issues in the immediate area.
2025-01-14 General Oilfield Services
Tier 3 Well is located within Watford City's Extra-Territorial Jurisdiction and on an aquifer, triggering extensive, non-routine location construction stipulations (closed mud system, no pit, impermeable liner, perimeter berm, etc.).
๐Ÿ“„ Permit Stipulations (Page 2 of 12)
Location construction is highly regulated and engineered beyond standard pads, requiring specific materials and methods.
2025-01-14 Mud / Fluids
Tier 3 Permit stipulation requires contact with specific NDIC Field Inspector (Marc Binns) prior to location construction and for onsite inspection due to aquifer and ETJ location.
๐Ÿ“„ Permit Stipulations (Page 2 of 12)
Creates a mandatory regulatory checkpoint before dirt work begins. Inspector may add site-specific stipulations on arrival.
2025-01-14 General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Drilling Rig & Crew Services
A larger drilling rig is scheduled to return to the location within a defined 90-day window after the initial spud (by ~8/8/2025). This is a time-sensitive mobilization opportunity.
Earthwork & Pad Construction
Pad expansion construction cannot begin until mandatory contact and inspection by NDIC Field Inspector Marc Binns. This is an immediate pre-construction gate.
Specialized Casing & Cementing
There is a declared possibility of needing an additional 9-5/8" Dakota casing string during drilling operations, creating a contingent opportunity.
Production Facility Automation & SCADA
Operator's BMP letter details plans for extensive SCADA, PLC, and alarm systems, indicating upcoming procurement and installation needs post-drilling.
Waste Hauling & Disposal
Drill cuttings are contractually designated for WISCO (or possibly Select Water Solutions), creating a locked-in opportunity for hauling and disposal services during drilling.