โ† Back to Daily Permits

๐Ÿ›ข๏ธ SHELL 153-89-5-16H-1

HUNT OIL COMPANY ยท Mountrail County, ND ยท File #42195 ยท Generated 2026-08-22 00:41

API
3306105566
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (5)

Tier Signal Date Service Impact
Tier 2 Operator requested Suspension of Drilling (SOD) for up to 90 days to drill surface hole with smaller rig (T&S Drilling Rig #2) and then move on larger rig (Nabors B21) within 90 days.โฐ TIME-SENSITIVE
๐Ÿ“„ Sundry Form - Suspension of Drilling
Two-rig strategy: small rig for surface hole (3-5 days), then larger rig for TD. Explicitly states intent to save cost and time. Requires immediate calls to NDIC after spud and when plug bumped.
2025-11-03 Drilling Rigs
Tier 3 Operator requested and received waiver to run tubing and packer, planning to flow well up 7'' casing after frac completion.
๐Ÿ“„ Sundry Form - Request for Consideration/Waiver (Tubing/Packer Waiver)
Deviates from standard completion design by eliminating tubing and packer, indicating a cost-saving or operational efficiency intent. Uses casing as production conduit with specific safety factor and monitoring protocols.
2026-07-20 Completions / Frac
Tier 3 Stipulation requires closed mud system with no cuttings pit, and all cuttings hauled to approved facility.
๐Ÿ“„ Permit Stipulations
Non-standard waste handling: mandates closed-loop system and offsite cuttings disposal, increasing logistics and cost.
2025-10-30 Mud / Fluids
Tier 3 Well name changed from SEVERANCE 153-89-4-9H-2 to SHELL 153-89-5-16H-1, and spacing unit expanded from 1280-acre to 3840-acre.
๐Ÿ“„ Sundry Form - Well Information / Well Name Change and Permit Modification sections
Significant redesign: well name change, lateral extension from ~10,000 ft to ~15,400 ft (based on bottom hole location change), and spacing unit tripled in size. Indicates a major revision in development plan.
2025-10-09 Completions / Frac
Tier 3 Anticollision report shows Level 3 warnings (closest approach <2.0 sigma) with nearby wells (e.g., Oakland 154-89-32-21H-1, Shell 3-05H).
๐Ÿ“„ Anticollision Report
High-risk drilling proximity to existing wells requires precise directional control and real-time monitoring to avoid collisions.
2025-09-23 Directional Drilling

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Directional Drilling & MWD/LWD
High-risk anticollision environment (Level 3 warnings) requires precise wellpath control and real-time surveying. Urgent need due to imminent drilling.
Cuttings Handling & Hauling
Permit stipulates closed mud system and all cuttings hauled to approved facility. Immediate requirement for drilling waste management services.
Pressure Monitoring & Flowback
Tubing/packer waiver requires pressure gauge on surface casing and flowback personnel on location during flowback. Specialized monitoring needed post-frac.
Pad Construction & Access Road Building
Detailed pad regrade plans and access road designs (~2,867 ft) by KLJ Engineering indicate imminent site construction activity.