๐Ÿ›ข๏ธ Cliffside 5103 41-7 6BX

Whiting Oil & Gas Corp. ยท McKenzie County, ND ยท File #42234 ยท Generated 2026-04-08 03:31

API
3305310685
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (4)

Tier Signal Date Service Impact
Tier 3 Drilling resumed after losses, with adjusted landing target to 10,662' TVD.
๐Ÿ“„ Geological Summary, page 4
Mid-drill adjustment to target depth post-losses.
2025-12-22 General Oilfield Services
Tier 3 Geological services began at Tyler formation; cuttings collected at 90' intervals vertical, 30' curve, 200' lateral; samples sent to Grand Forks.โฐ TIME-SENSITIVE
๐Ÿ“„ Geological Summary, page 3
Detailed sampling protocol beyond standard, with remote geosteering.
2025-11-09 General Oilfield Services
Tier 3 Waiver requested for open hole logs, citing offset well PAULSON 13-14H within 1 mile with sufficient logs.
๐Ÿ“„ Sundry Form for Well File No.: 42234, Request for Consideration/Waiver
Non-standard regulatory approval to skip open hole logging, potentially reducing costs and time.
2025-08-19 Regulatory / Permitting
Tier 3 Drilling paused due to fluid losses in lower Charles and Mission Canyon; zones cemented and reamed; decision to batch drill Dakota strings on remaining wells.
๐Ÿ“„ Geological Summary, page 3
Unexpected operational challenge leading to adaptive drilling strategy.
Relative General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Directional Drilling and MWD Services
Well reached TD in December 2025; directional supervisors and MWD engineers actively involved through curve and lateral phases.
Mud Engineering and Geological Monitoring
Mud services and geologists engaged from spud in November 2025 through completion.
Completion and Stimulation
Well awaiting completion post-TD December 27, 2025; potential for immediate stimulation services.