โ† Back to Daily Permits

๐Ÿ›ข๏ธ KOLSCH 3119-2BH

KODA RESOURCES OPERATING, LLC ยท Divide County, ND ยท File #42339 ยท Generated 2026-09-30 06:46

API
3302301682
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (5)

Tier Signal Date Service Impact
Tier 3 Major lateral trajectory shift: KOP moved 721' east, 7" casing point/lateral/BHL shifted ~860' east from original plan.
๐Ÿ“„ Permit Modification 'PROPOSED WORK' section, page 7 of 10, dated 9/1/2026
This is a substantial redesign of the well path, not a minor adjustment. It requires new anti-collision analysis, survey planning, and likely changes to geosteering targets.
2026-09-01 Directional Drilling
Tier 3 Operator secured approval to waive open-hole porosity/resistivity logs, relying on data from offset well Bock 3624-1BH.
๐Ÿ“„ Sundry Notice Form, 'DESCRIPTION (OPERATOR)' section, dated 07/07/2026
This is a non-routine regulatory approval that reduces standard data acquisition costs. It indicates the operator is confident in subsurface correlation from a nearby well.
2026-07-07 General Oilfield Services
Tier 3 Operator formally requested a waiver from the mandatory 3-business-day waiting period before commencing operations after permit approval.โฐ TIME-SENSITIVE
๐Ÿ“„ Affidavit letter dated September 11, 2025
Waiving the waiting period shows intent to begin construction and drilling immediately upon permit approval, indicating urgency and compressed timeline for pad development.
2025-09-11 Regulatory / Permitting
Tier 3 Plans to cement the 4-1/2" production liner using a 'wet shoe with the ability to frac out the toe'.
๐Ÿ“„ Drilling Plan, 'Completion Program' section
A 'wet shoe' completion is a specific technique that influences cementing design, stage isolation, and initial fracture initiation, differing from standard cemented liner or plug-and-perf designs.
Relative Completions / Frac
Tier 3 MWD Contractor is pre-selected as 'KLX Directional' in the drilling plan.
๐Ÿ“„ Drilling Plan, '1. Estimated Formation Tops' section
The directional/MWD vendor is explicitly named in the well plan, indicating a declared service contractor ahead of spud. This is a direct signal of awarded or intended work.
Relative Directional Drilling

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Directional Drilling / MWD / Geosteering
The major lateral trajectory shift (KOP and BHL moved ~860' east) requires immediate updated well planning, anti-collision analysis, and execution services. KLX Directional is already named as the MWD contractor.
Cementing
The plan to use a 'wet shoe' completion for the production liner requires specialized cementing design and execution to facilitate fracturing out the toe.
Civil Construction & Earthwork
The operator has requested a waiver from the 3-day waiting period post-permit. If granted, location construction could begin imminently, driving urgency for pad building, berm construction, and access road work.
Cased Hole Logging
While open-hole logs are waived, the permit requires a CBL on the 9 5/8" string, and the sundry notes a GR-CBL will be run from TD to ground level, securing this service.
Waste Hauling / Landfill Services
The drilling plan specifies a closed-loop system with all drill cuttings disposed at '13 Mile Landfill, Williston, ND', indicating a pre-determined disposal site and hauling need.