๐Ÿ›ข๏ธ RELLA E 5303 13-17 2BX

OASIS PETROLEUM NORTH AMERICA LLC ยท Williams County, ND ยท File #42380 ยท Generated 2026-08-22 00:59

API
3310506716
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (5)

Tier Signal Date Service Impact
Tier 2 Detailed 'Wet Shoe' configuration described: Cement job intentionally over-displaced by 7 barrels, creating ~400' of uncemented annulus at liner toe to allow pump-down of first stage perforating guns on wireline.
๐Ÿ“„ Well Details / Discussion section (following 'ANTI-COLLISION STATEMENT')
This is a specific, non-standard completion design choice aimed at cost reduction ('avoiding the more expensive option of perforating on tubing or with a tractor'). It reveals precise operational intent for the toe stage.
Unknown Completions / Frac
Tier 3 Anticipated commencement date for drilling is January 3, 2026, with an estimated 30 drilling days.โฐ TIME-SENSITIVE
๐Ÿ“„ Drilling Plan section: 'ANTICIPATED STARTING DATES'
Provides a forward-looking schedule for major operations, distinct from permit or spud dates. Indicates winter drilling campaign planning.
2026-01-03 Drilling Rigs
Tier 3 Specific regulatory stipulation: 'The south setback is based on a production liner cemented in the lateral with a wet shoe and the ability to frac out the shoe.'
๐Ÿ“„ Permit Stipulations (Page 2 of 10)
The approval of a reduced south setback (150') is explicitly tied to a specific well design choice ('wet shoe' configuration). This is a conditional approval based on engineering design.
2025-10-07 Completions / Frac
Tier 3 Operator requested and received approval to waive open hole logging requirement, citing offset well RELLA 17-20H (NDIC# 21099) within a mile as sufficient for formation tops. Will run GR-CBL from TD to ground level instead.
๐Ÿ“„ Open Hole Log Waiver Sundry Form (FORM ID: 274606)
Indicates a cost-saving operational deviation from standard regulatory requirements, relying on existing subsurface data rather than new acquisition. Shows confidence in offset well control.
2025-10-07 Drilling Rigs
Tier 3 Operator submitted an 'AFFIDAVIT AFFIRMING DRILL-BACK NOTIFICATION' to adjacent operator Devon Energy on 10/3/2025, as required for wellbores exiting the target spacing unit.
๐Ÿ“„ AFFIDAVIT AFFIRMING DRILL-BACK NOTIFICATION
Formal, time-sensitive regulatory compliance step triggered by the well path design. Demonstrates proactive engagement with offset operator (Devon) and adherence to Order No. 31848.
2025-10-03 Drilling Rigs

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Wireline Perforating (Toe Stage)
The approved 'wet shoe' design specifically enables and requires pump-down perforating on wireline for the first stage, creating a near-term opportunity post-drilling.
Cementing & Fluids Engineering
The wet shoe design requires precise cement over-displacement (7 bbls). The detailed cement program with specific additive packages (extenders, dispersants, expanding agents) indicates need for specialized engineering and pumping services.
Drilling Waste / Cuttings Disposal
Permit lists eight specific licensed disposal facilities, but operator states cuttings 'will be hauled to the closest available facility.' This creates competition among listed disposal vendors (e.g., Secure Energy, Tervita, Ideal Oilfield Disposal) based on proximity and availability around the planned Jan 2026 spud.
Directional Drilling / MWD Services
Complex anti-collision environment with many offset wells requires high-precision surveying and real-time guidance. The plan specifies survey tools (OWSG MWD+IFR1) and frequent survey intervals.