โ† Back to Daily Permits

๐Ÿ›ข๏ธ Big Stone 1 SWD

FIREBIRD SERVICES, LLC ยท Williams County, ND ยท File #42383 ยท Generated 2026-08-22 00:59

API
3310506717
Target Formation
Inyan Kara (Dakota Group)
Confidence
High

๐Ÿ“Š Signals (5)

Tier Signal Date Service Impact
Tier 3 Operator requested and received waiver from open hole logging requirements, leveraging offset well data to establish formation tops.
๐Ÿ“„ Well Sundry Form - Request for Consideration/Waiver
Demonstrates proactive regulatory strategy to reduce well construction costs and time by avoiding redundant logging.
2026-06-17 Regulatory / Permitting
Tier 3 Operator requested significant MAIP increase from 1318 psi to 2459 psi shortly after well completion, based on Hazen-Williams friction calculations.โฐ TIME-SENSITIVE
๐Ÿ“„ Well Sundry Form - Maximum Injection Pressure Increase
Immediate post-completion pressure uprate indicates either initial design conservatism or discovered higher injectivity, enabling higher throughput.
2026-02-20 General Oilfield Services
Tier 3 Pressure test of high-pressure injection line (4" Flexsteel 2250 psi) performed at 2250 psi for 30 mins, exceeding permitted MAIP at the time.
๐Ÿ“„ Well Sundry Form - Notification of Work Performed
Line tested to pressure above initial permitted MAIP, indicating infrastructure built for future pressure increases.
2026-02-04 General Oilfield Services
Tier 3 MIT performed and passed on 2025-12-30, with next test due in 5 years (2030-12-30), establishing well integrity baseline.โฐ TIME-SENSITIVE
๐Ÿ“„ Well Integrity Report
Early MIT pass establishes operational confidence and sets a long-term compliance calendar.
2025-12-30 General Oilfield Services
Tier 3 Tank diking variance approved contingent on submission of as-built schematic, indicating non-standard containment design.
๐Ÿ“„ Permit Stipulations
Regulatory granted flexibility on containment sizing suggests operator negotiated based on pad-wide containment strategy.
2025-10-08 General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

High-Pressure Pumping & Flowline Services
MAIP increased to 2459 psi, indicating need for high-pressure injection pumps and flowlines rated for sustained operation above 2200 psi.
Well Integrity Testing & Monitoring
MIT passed with next test due in 2030, but ongoing monitoring likely required for high-rate injection; pressure and vibration monitoring referenced in SCADA.
Facility Construction & Earthwork
Pad involved significant cut/fill (over 100k cu yds); future pads for operator may require similar large-scale grading and containment construction.
Regulatory & Permitting Support
Operator actively pursues waivers and variances (logging, diking); specialists can assist in navigating similar requests for efficiency gains.