๐Ÿ›ข๏ธ LOOMER 11-2 XE 1H

DEVON ENERGY WILLISTON, L.L.C ยท McKenzie County, ND ยท File #42421 ยท Generated 2026-09-14 03:56

API
3305310720
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (6)

Tier Signal Date Service Impact
Tier 3 Well pad is located within Watford City's Extra-Territorial Jurisdiction and on an aquifer, triggering extensive site-specific stipulations including closed mud system, impermeable liner, fencing, and mandatory NDIC field inspection prior to construction.
๐Ÿ“„ Permit Stipulations
Location triggers a high level of regulatory oversight and environmental controls, increasing planning and compliance complexity.
2026-03-19 Mud / Fluids
Tier 3 Permit requires a mud logger on-site from ground level to TD of the 17-1/2-inch surface hole, with samples at no greater than 30' intervals.
๐Ÿ“„ Permit Stipulations
This is a specific, mandated service requirement tied to the deep surface casing and Mowry Formation prohibition.
2026-03-19 Mud / Fluids
Tier 3 Permit requires multiple Cement Bond Logs (CBL): radial/ultrasonic on deep-set surface casing, on the 9-5/8-inch intermediate string, and a standard CBL on the 7-inch casing.
๐Ÿ“„ Permit Stipulations
This is a non-routine, multi-stage cement verification mandate beyond standard practice.
2026-03-19 General Oilfield Services
Tier 3 Operator requested and received a 90-day suspension of drilling to use a smaller rig for surface hole only, planning to spud with it and return with a larger rig within 90 days.โฐ TIME-SENSITIVE
๐Ÿ“„ Sundry Form - Suspension of Drilling
This is a non-routine operational strategy to save costs by using two different rigs, creating a defined window for a second rig move.
2026-02-23 Drilling Rigs
Tier 3 Operator requested and received a waiver for the on-site filter sock container, stating they do not use filter media during drilling.
๐Ÿ“„ Sundry Form - Filter Sock Container Waiver
Devon is opting out of a standard regulatory requirement, indicating a specific waste management practice.
2026-02-23 Regulatory / Permitting
Tier 3 A 40-arm caliper log will be run prior to installing the 9-5/8-inch Dakota string to validate casing wear predictions.
๐Ÿ“„ Proposed Drilling Plan / Anticipated Casing Wear
Specific advanced logging tool mandated due to planned deviation and wear modeling.
Relative General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Mud Logging
Mandated by permit from ground level to TD of surface hole with 30' sample intervals; required before drilling deeper.
Cement Bond Logging (CBL/Ultrasonic)
Multiple CBLs are required by permit on surface, intermediate, and production casing strings, creating sequential service events.
Advanced Caliper Logging
A 40-arm caliper log is specifically planned prior to setting the 9-5/8-inch intermediate casing to validate wear models.
Drilling Rig Services
A sequenced opportunity: a smaller rig for surface hole (spud anticipated 3/23/26), followed by a larger rig to TD within a 90-day window.
Environmental & Site Construction
Pad location on an aquifer and in a city's ETJ mandates closed mud system, impermeable liner, fencing, and berms, requiring specialized contractors.