πŸ›’οΈ AB-Edward Fox Federal 29-26H MB

MUREX PETROLEUM CORPORATION Β· Williams County, ND Β· File #42453 Β· Generated 2026-08-22 01:19

API
3310506736
Target Formation
Middle Bakken
Confidence
High

πŸ“Š Signals (8)

Tier Signal Date Service Impact
Tier 2 Wet shoe liner design with 100' uncemented annulus at toe, requiring frac plug isolation for Stage 1.
πŸ“„ WET SHOE SCHEMATIC and Discussion
Unconventional completion design increases operational complexity and requires precise plug-and-perf execution to avoid fracturing out the shoe.
Unknown Completions / Frac
Tier 3 Mandatory closed mud system, no drilling pit, impermeable liner on entire location, and specific casing/cementing requirements for rat/mouse holes due to Tioga Extra-Territorial Jurisdiction.
πŸ“„ STIPULATIONS section
Stringent municipal-level environmental controls exceed standard NDIC requirements, imposing additional cost and operational constraints.
2026-06-18 Mud / Fluids
Tier 3 Mandatory CBL on 9-5/8" intermediate casing prior to setting 7" casing, plus standard CBL on 7" casing.
πŸ“„ STIPULATIONS section
Extra cement bond log requirement indicates regulatory concern about Dakota water string integrity, adding time and cost.
2026-06-18 General Oilfield Services
Tier 3 Permit modification to change surface hole to 17.5", surface casing to 13.375", and add a Dakota string (12.25" hole).
πŸ“„ PROPOSED WORK section
Non-standard casing design indicates specific geomechanical or regulatory challenges requiring larger surface hole and additional intermediate string.
2026-06-18 General Oilfield Services
Tier 3 Gas marketing affidavit states target first production ~7/1/2026 with combined peak gas rate of 4,600 Mcf/d, and discussions with Chord Energy and Hess for gas takeaway.⏰ TIME-SENSITIVE
πŸ“„ AFFIDAVIT OF INFORMATION section
Explicit gas marketing timeline and volume commitments signal impending mid-2026 completion activity and need for gas infrastructure.
2025-10-24 General Oilfield Services
Tier 3 Drillback waiver affidavit confirms operator is drilling six wells from same pad into adjacent spacing units, with trajectories entering Bakken outside target unit.
πŸ“„ DRILLBACK WAIVER section
Multi-well pad with extended laterals crossing unit boundaries requires regulatory waiver and demonstrates aggressive development strategy.
2025-10-23 Completions / Frac
Tier 3 Waiver requested for open hole logs; only cased hole logging planned unless otherwise required.
πŸ“„ ELECTRIC LOGGING PROGRAM section
Operator is avoiding standard open hole logging, relying on mud logging and cased hole evaluation, which reduces data collection but saves cost/time.
Unknown Mud / Fluids
Tier 3 Designated as a TIGHT HOLE with restricted access to rig floor, mudlogging unit, and data areas; communication coordinated from Houston office.
πŸ“„ SECURITY & COMMUNICATIONS section
Unusual secrecy measures limit onsite access and data flow, suggesting competitive sensitivity or proprietary drilling/completion techniques.
Unknown Mud / Fluids

πŸ’‘ Operator Intent

πŸ”§ Service Operator Relevance

Casing and Cementing
Non-standard casing sizes (17.5" hole, 13.375" surface, 9-5/8" intermediate) and wet shoe liner design require specialized tubulars and cementing procedures; multiple CBL runs needed.
Directional Drilling and Surveying
Extended lateral (~15,500' reach) with precise anti-collision requirements due to dense offset well environment; tight hole restrictions may limit real-time data access.
Environmental and Containment
Tioga Extra-Territorial Jurisdiction mandates closed mud system, impermeable liner, perimeter berms, and specific rat/mouse hole casingβ€”exceeding standard NDIC rules.
Completion and Stimulation
Wet shoe design requires careful plug-and-perf execution to isolate shoe; six-well pad implies high-volume frac schedule mid-2026 to meet gas sales timeline.
Gas Midstream and Compression
Target peak gas rate of 4,600 Mcf/d from pad by ~7/1/2026 requires confirmed takeaway with Chord Energy and Hess; infrastructure must be ready by Q2 2026.