| Tier | Signal | Date | Service Impact |
|---|---|---|---|
| Tier 3 |
Operator requested and received approval to waive open hole logging requirements, citing offset well data within one mile. ๐ Well Sundry Form - Open Hole Log Waiver Avoids routine data acquisition cost and time. Demonstrates operator's reliance on existing subsurface data and confidence in regional geology, reducing well evaluation expenses. |
2026-06-16 | General Oilfield Services |
| Tier 3 |
Drone survey performed for as-built pad containment volume calculation (May 11, 2026) and for pre-construction topography (June 9, 2025). ๐ As-Built Plat Notes & Pad Layout sheet Use of drone technology for regulatory compliance (containment volume verification) and pre-construction planning. Represents modern, efficient surveying method adoption. |
2026-05-11 | General Oilfield Services |
| Tier 3 |
First injection occurred on 5/5/2026, just two days after the MIT test (3/16/2026) and before formal completion report submission (5/13/2026). ๐ Well Sundry Form - Date of First Injection & Well Integrity Report Injection commenced rapidly after mechanical integrity test, indicating operational readiness and urgency to begin disposal. Suggests pre-commissioning of surface facilities was completed ahead of schedule. |
2026-05-05 | General Oilfield Services |
| Tier 3 |
Operator successfully obtained a tank diking variance for the SWD facility, contingent on submission of an as-built site schematic. ๐ Permit stipulations section, page 3 of 11 Indicates regulatory flexibility granted for facility design, reducing containment construction requirements. This variance is a non-standard approval that reduces capital cost and design constraints for the operator. |
2025-11-18 | General Oilfield Services |
| Tier 3 |
Two rapid, successive Maximum Allowable Injection Pressure (MAIP) increases requested and approved within one month (from 1494 psi to 1846 psi to 2048 psi).โฐ TIME-SENSITIVE ๐ Well Sundry Forms - Maximum Injection Pressure Increase Shows operational urgency to maximize injection capacity. The 554 psi total increase (37% from original) within weeks indicates either higher-than-expected disposal demand or pressure optimization post-commissioning. |
Relative | Drilling Rigs |
| Tier 3 |
Freshwater well sampling affidavit reveals one well (15810104BA) was inoperable during permit application, with commitment to sample in Spring 2026 after repair.โฐ TIME-SENSITIVE ๐ Appendix C - Freshwater Wells within 1-mile Creates a future regulatory obligation (Spring 2026) for freshwater sampling. Shows operator's proactive engagement with landowners and commitment to deferred compliance items. |
Relative | General Oilfield Services |