๐Ÿ›ข๏ธ T Johnson 32-5-8 4HF

Phoenix Operating, LLC ยท Mountrail County, ND ยท File #42508 ยท Generated 2026-08-22 01:33

API
3306105620
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (5)

Tier Signal Date Service Impact
Tier 2 Operator secured multiple regulatory waivers pre-spud: Filter Sock Container, Tubing/Packer, Drill Cutting Samples (vertical portion), and Open Hole Logs.
๐Ÿ“„ Multiple WELL SUNDRY FORMS (Form IDs: 288458, 288483, 288455, 288454)
Demonstrates proactive regulatory strategy to reduce operational burden and cost. The drill cuttings waiver relies on samples from an offset well on the same pad (#42507), indicating pad-scale planning.
2025-12-16 Regulatory / Permitting
Tier 3 Operator requested and received a 90-day suspension of drilling after spudding surface hole with a smaller rig, planning to return with larger rig to complete well within 90 days.โฐ TIME-SENSITIVE
๐Ÿ“„ WELL SUNDRY FORM - Request for Consideration/Waiver - Suspension of Drilling
Reveals a staged drilling approach to save costs, creating a defined window for rig and service mobilization. Indicates operator is optimizing capital by using a smaller rig for surface section.
2026-02-02 Drilling Rigs
Tier 3 MWD failure occurred at 8,950' MD (KOP) on March 13, 2026, requiring a trip out of hole.
๐Ÿ“„ Sample Descriptions section (page 9)
An unplanned downhole tool failure during a critical operation (at kick-off point) caused non-productive time. Highlights potential reliability issues or harsh drilling conditions.
Relative General Oilfield Services
Tier 3 Well is part of a five-well pad, with geological steering and sample collection coordinated across pads (e.g., cuttings waiver references offset well 42507).
๐Ÿ“„ Geological Summary and Drill Cutting Samples Waiver Sundry
Reveals a multi-well development campaign, not a single well. Operational and regulatory decisions are made at the pad level.
Relative Regulatory / Permitting
Tier 3 Operator notified Slawson Exploration Company, Inc. as required for wells entering adjacent spacing units, per NDIC orders.
๐Ÿ“„ STATE OF COLORADO affidavit following email from NDIC
Demonstrates compliance with inter-operator coordination rules for extended-reach laterals. Confirms wellbore traverses into units operated by others.
2025-11 Completions / Frac

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Drilling Rig Services
A larger rotary rig was scheduled to move onto location within 90 days of the initial spud (Feb 2-3, 2026) to complete the well. This creates a near-term, scheduled rig mobilization opportunity.
Completion & Stimulation Services
The well file concludes with 'This well is waiting for completion.' Following the March 2026 TD, completion is the next major phase, requiring frac crews, pumping services, sand, water, and wellhead equipment.
Waste/Disposal Services
The drilling plan explicitly names Prairie Disposal LLC, but the volume of cuttings from a ~25,000' MD well represents a significant, locked-in disposal event that may be repeatable across the pad.
Directional Drilling / MWD Services
The MWD failure at KOP indicates a recent tool reliability event. For future wells on the pad, the operator may be evaluating alternative service providers or technologies.