๐Ÿ›ข๏ธ HERCULES 1-12-13 3H

Phoenix Operating LLC ยท Burke County, ND ยท File #42558 ยท Generated 2026-08-31 03:39

API
3301302006
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (5)

Tier Signal Date Service Impact
Tier 2 Operator requested and received approval for suspension of drilling for up to 90 days after spudding surface hole with smaller rig, with intention to return with larger rig to complete well within that window.โฐ TIME-SENSITIVE
๐Ÿ“„ Suspension of Drilling Sundry (FORM ID: 296089)
Reveals a staged drilling approach to achieve cost and time savings, creating a defined 90-day window for the larger rig mobilization and completion drilling.
2026-02-02 Drilling Rigs
Tier 2 Operator requested and received a variance from tubing/packer requirement based on casing specs and completion design assurances.
๐Ÿ“„ Tubing/Packer Waiver Sundry (FORM ID: 288127)
Indicates a non-standard completion design that relies on casing integrity rather than a packer, which could influence subsequent well intervention strategies.
2025-12-15 General Oilfield Services
Tier 3 Operator changed the sampling waiver plan mid-pad, shifting designated sample well from 1H to 7H to improve rig efficiency.
๐Ÿ“„ Drill Cutting Samples Waiver Sundry (FORM ID: 330666)
Shows operational adaptability and real-time optimization decisions on a multi-well pad, overriding a prior plan.
2026-08-07 Drilling Rigs
Tier 3 Operator received approval for a pilot project waiving onsite mud logging requirement, implementing an off-site sample collection SOP with rig personnel trained by Core Geologic.
๐Ÿ“„ Intent No On-site Mud Logging Sundry (FORM ID: 329339) and attached SOP
Represents a significant operational shift from standard practice, reducing onsite personnel and changing the sample collection workflow.
2026-07-31 Mud / Fluids
Tier 3 Operator proactively coordinated with Steel Reef regarding an abandoned, unlocatable poly gas line traversing the pad, committing to locate and mitigate during construction.
๐Ÿ“„ Email correspondence dated 2025-12-11
Reveals a pre-construction risk mitigation effort involving a third-party pipeline operator, indicating potential for construction delays or specialized services.
2025-12-11 General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Drilling & Rig Services
A larger rotary rig is scheduled to mobilize within a 90-day window after a smaller rig spuds the surface hole (anticipated spud 2026-08-10). This creates a time-bound mobilization opportunity.
Environmental & Waste Disposal
Drill cuttings are contractually destined for Smoky Butte Environmental LLC, and a filter sock container waiver means no on-site filter media handling is planned during drilling.
Construction & Earthwork
Pad construction must address an abandoned Steel Reef pipeline, requiring possible location services, coordination, and potential removal, adding complexity to earthwork.
Wellsite Training & Logistics
Rig personnel require training from Core Geologic on sample collection procedures for the off-site mud logging pilot, creating a service need tied to rig moves.