๐Ÿ›ข๏ธ ALE 2335-3BHN

KODA RESOURCES OPERATING, LLC ยท Divide County, ND ยท File #42594 ยท Generated 2026-11-25 04:23

API
3302301727
Target Formation
BAKKEN
Confidence
High

๐Ÿ“Š Signals (4)

Tier Signal Date Service Impact
Tier 3 Mandatory pre-construction onsite inspection and specific construction stipulations due to aquifer location.โฐ TIME-SENSITIVE
๐Ÿ“„ Permit stipulations on first page and page 2.
The well is on an aquifer, triggering non-standard requirements: a closed mud system with no pit, an impermeable liner for the entire location, and a perimeter berm. The operator must contact the NDIC Field Inspector (Marc Binns) prior to construction.
2026-09-18 Mud / Fluids
Tier 3 Operator requested and received approval for a permit modification to change surface and bottom hole locations.
๐Ÿ“„ PROPOSED WORK section on page 7.
The document shows the operator changed the surface hole location from 676' FNL 1869' FEL to 510' FNL 1993' FEL and the bottom hole location from 200' FNL 2110' FEL to 200' FNL 1503' FEL, indicating active trajectory optimization.
2026-09-18 Directional Drilling
Tier 3 MWD contractor pre-selected for the well in a drilling plan dated July 29, 2026.โฐ TIME-SENSITIVE
๐Ÿ“„ Drilling Plan section within the file.
The drilling plan explicitly names 'KLX Directional' as the MWD Contractor. This is a non-routine disclosure of a pre-selected service provider for the upcoming drilling operation.
2026-07-29 Directional Drilling
Tier 3 Mandatory on-site leak-proof container for filter sock disposal from spud through flowback.
๐Ÿ“„ Operator assertions and a regulatory letter dated July 29, 2026.
A regulatory letter reiterates the requirement for a covered, leak-proof, placarded container on site from spud through clean-out, completion, and flow-back whenever filtration is used. The operator asserts understanding of this rule.
2026-07-29 General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Environmental & Site Construction
The aquifer stipulation requires an impermeable liner, closed mud system, and perimeter berm. The approved permit (2026-09-18) means these site construction activities are imminent or pending.
Directional Drilling / MWD
KLX Directional is named as the MWD contractor in the 2026 drilling plan. The recent permit modification (Sept 2026) confirms the well is moving forward, signaling imminent mobilization for directional services.
Surveying
The permit modification involved changes to surface and bottom hole locations. This likely required recent surveying work, and ongoing pad development (8 wells) suggests continued need for surveying services.
Waste Hauling / Disposal
The drilling plan specifies a closed loop system with cuttings disposal at '13 Mile Landfill, Williston, ND.' This establishes a pre-selected disposal facility and creates a recurring service need for hauling.