| Tier | Signal | Date | Service Impact |
|---|---|---|---|
| Tier 2 | Liner to be run with wet shoe and ability to frac out the toe, using plug and perf method for stimulation without a frac string Completion Program |
Relative | Completions / Frac |
| Tier 3 | Request for waiver of three-day waiting period prior to construction/operations following APD approval, citing majority interest ownership in multiple DSUs⏱ URGENT AFFIDAVIT- REQUEST FOR WAIVER TO THREE-DAY WAITING PERIOD |
2025-12-15 | Regulatory / Permitting |
| Tier 3 | Waiver request from NDIC Order 31973, as operator of adjacent spacing unit, to avoid providing directional plans to other operators Letter to Todd Holweger dated December 5, 2025 |
2025-12-05 | Directional Drilling |
| Tier 3 | Submission of anti-collision avoidance modeling based on all known offset wells within vicinity, including specific separation factors and warnings KLX Anticollision Report dated 24 November, 2025 |
2025-11-24 | Directional Drilling |
| Tier 3 | Planned waiver of open hole logs, with sundry to be submitted Evaluation Program section |
Relative | Regulatory / Permitting |
| Tier 3 | Use of produced Bakken salt water for production hole mud, with closed loop system and disposal at 13 Mile Landfill Drilling Fluids Program |
Relative | Mud / Fluids |