๐Ÿ›ข๏ธ MHA BULLSNAKE 4892 14-28 1BHP

OASIS PETROLEUM NORTH AMERICA LLC ยท Dunn County, ND ยท File #42650 ยท Generated 2026-11-26 07:10

API
3302505134
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (5)

Tier Signal Date Service Impact
Tier 3 Regulator mandates monthly conventional rig updates to the DMR and immediate calls to the field inspector upon spud and when the conventional rig moves back on.
๐Ÿ“„ Reviewer Comments on Suspension of Drilling Sundry
Imposes specific, non-routine reporting and coordination requirements that increase operator administrative burden and require precise field communication.
2026-06-26 Drilling Rigs
Tier 3 Operator requests and is granted a waiver for open hole logs, relying on offset well data, but will run a GR-CBL from TD to ground level.
๐Ÿ“„ Open Hole Log Waiver Sundry
Deviates from standard logging requirements, indicating confidence in offset data but still committing to a specific cased-hole log.
2026-03-03 Regulatory / Permitting
Tier 3 A detailed core and sample collection directive is issued by the State Geologist, with strict intervals and deadlines (30 days for samples, 180 days for cores post-drilling).โฐ TIME-SENSITIVE
๐Ÿ“„ Cores and Samples Letter
Imposes a specific, mandatory sample collection and submission protocol with civil penalty risks, requiring dedicated on-site personnel and logistics.
2026-01-20 General Oilfield Services
Tier 3 Permit approval is conditioned on submitting an as-built directional survey and frac stimulation procedures for prior approval due to a U-turn well design with lateral close to unit boundary.
๐Ÿ“„ Permit Conditions of Approval
Highlights a non-standard well path (U-turn) requiring special regulatory review of completion design before operations can proceed.
2026-01-15 Directional Drilling
Tier 3 Operator plans a two-rig sequence: a small 'spudder' rig to drill surface hole and set casing, then a larger conventional rig to drill to TD, with up to 90 days between spud and the larger rig move-on.โฐ TIME-SENSITIVE
๐Ÿ“„ Sundry Form for Suspension of Drilling
Reveals a staged, cost-saving drilling strategy that creates two distinct rig mobilization/demobilization events and a 90-day window for the larger rig contractor.
Relative Drilling Rigs

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Drilling Contractors
Two distinct rigs are planned: a spudder rig scheduled for October 2026 for surface hole, followed by a conventional rig within 90 days after that spud. This creates two mobilization events.
Coring & Sample Management
A mandatory, detailed sample collection program is required starting at the Base of the Last Charles Salt, with strict washing, drying, boxing, and shipping deadlines post-drilling.
Cementing & Cased Hole Logging
While open hole logs are waived, a GR-CBL from TD to ground level is required. The detailed cementing program for surface, production, and liner strings indicates significant cementing services will be needed.
Waste Management / Solids Disposal
Operator lists nine licensed facilities for dry cuttings disposal and is required to have a leak-proof filter sock container on site from spud through flowback, indicating need for waste hauling and disposal services.
Surveying & Civil Construction
Pad construction involves 66,700 CY of excavation and 56,850 CY of embankment. KLJ Engineering is already engaged, but earthwork, grading, and road construction services will be required to execute these plans.