๐Ÿ›ข๏ธ TUFTO 6-7-18-19F 3H

DEVON ENERGY WILLISTON, L.L.C ยท Williams County, ND ยท File # ยท Generated 2026-02-11 18:35

API
3310506797
Target Formation
Bakken
Confidence
High

๐Ÿ“Š Signals (5)

Tier Signal Date Service Impact
Tier 2 Wellbore design includes lateral cemented with wet shoe and ability to frac out the shoe, indicating advanced completion technique for toe initiation without wireline intervention.
๐Ÿ“„ Bakken Setback Summary Statement and PROPOSED DRILLING PLAN
Non-standard wet shoe setup for frac-out is a specialized design choice not typical in all horizontal Bakken wells, potentially reducing operational risks and costs in toe preparation.
Unknown Completions / Frac
Tier 3 Permit approved with future submission and approval dates (submitted 01/22/2026, approved 02/06/2026), implying planned timing for operations.โฐ TIME-SENSITIVE
๐Ÿ“„ SUBMITTED BY and APPROVED BY sections
Future dates suggest delayed or scheduled activity, not immediate, potentially aligning with broader Devon campaign in the area.
2026-01-22 Drilling Rigs
Tier 3 CBL required on 13-3/8-inch surface casing, 9-5/8-inch intermediate, and 7-inch casing, with specific compressive strength timing and zero-pressure pass.
๐Ÿ“„ Conditions of Approval - Cementing requirements
Enhanced cement verification protocols indicate potential for cement integrity issues in this formation or unit, prompting extra QA measures.
Unknown General Oilfield Services
Tier 3 Well located within 1000 feet of occupied dwelling, requiring specific assertions and potential permit conditions on facility placement.
๐Ÿ“„ Operator Assertions and permit conditions
Proximity to dwelling necessitates tailored design for noise/flare management, revealing operator's adaptation to urban-adjacent drilling.
Unknown General Oilfield Services
Tier 3 Mandatory on-site mud logger from ground level to total depth of 17-1/2-inch surface hole, with no intentional deviation in surface casing.
๐Ÿ“„ Conditions of Approval
Stringent logging and deviation restrictions in surface hole suggest heightened regulatory scrutiny or operator caution in this specific spacing unit, beyond standard NDIC requirements.
Unknown Mud / Fluids

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Mud logging and cement bond logging services
Mandatory requirements effective immediately upon spud, with approval dated 02/06/2026, creating immediate opportunity for specialized logging contractors in surface and intermediate casings.
Indirect heating equipment supply
Specified use of Steffes or JW Williams heaters for facilities, timed with potential operations start post-approval, allowing vendors to prepare inventory for winter drilling.