๐Ÿ›ข๏ธ RS-Bette- 156-92-0128H-4

HESS BAKKEN INVESTMENTS II, LLC ยท Mountrail County, ND ยท File #42811 ยท Generated 2026-04-07 03:14

API
3306105673
Target Formation
Bakken
Confidence
High

๐Ÿ“Š Signals (4)

Tier Signal Date Service Impact
Tier 2 Permit approved with conditional setbacks requiring production liner cemented in lateral with wet shoe for frac-out capability, enabling tighter boundary spacing in 2400-acre unit.โฐ TIME-SENSITIVE
๐Ÿ“„ Permit Information - Stipulation and Conditions of Approval
Non-standard setback allowances based on specific cementing and frac techniques, not typical for basic horizontal permits.
2026-04-02 Completions / Frac
Tier 2 Completion design specifies cemented liner with wet shoe for intentional over-displacement by 2 bbls, followed by plug-and-perf stages.
๐Ÿ“„ Completion Equipment and Drilling Prognosis sections
Wet shoe design allows frac initiation from shoe, a specialized technique not standard in all Bakken completions.
Unknown Completions / Frac
Tier 3 Operator requests waiver for adjacent unit notice under Order 31848, citing self-ownership of adjacent spacing unit, avoiding disclosure of drilling plans to third parties.
๐Ÿ“„ Letter from Levi S. Greenly to Todd L. Holweger, dated July 15, 2025
Waiver leverages internal ownership to bypass regulatory disclosure requirements, uncommon in multi-operator fields.
2025-07-15 Regulatory / Permitting
Tier 3 Anti-collision report shows planned wellbore within 1.5 separation factor of existing wells, using gamma ray geo-steering and real-time surveys every 93-100 ft.
๐Ÿ“„ Anti-Collision Statement and Report dated 03 July, 2025
Detailed anti-collision protocols exceed basic permit requirements, highlighting proactive risk management in dense infill pad.
2025-07-03 Directional Drilling

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Directional Drilling and Anti-Collision Services
Anti-collision report dated July 2025 indicates immediate need for real-time surveys and geo-steering; Hess's standards call for frequent checks, creating opportunity post-permit approval.
Cementing and Liner Services
Permit approval April 2026 requires specific cement volumes and centralizer placements; wet shoe design implies urgency for specialized liner installation ahead of drilling commencement.
Hydraulic Fracturing
Pre-selected Halliburton for diesel-free HF; with spud notification required 3 business days post-publication, frac services may be timed shortly after drilling completion.