| Tier | Signal | Date | Service Impact |
|---|---|---|---|
| Tier 2 |
Production liner cemented with wet shoe and no ability to frac out the shoe; bridge plug to be set at toe prior to frac. ๐ Page 5-6, Wellbore Information and Completion & Perforation; also detailed in geologic prognosis and liner specs Specific wet shoe design with bridge plug isolation for frac initiation, a non-standard completion choice to enable toe-stage injection without frac-out capability. |
Unknown | Completions / Frac |
| Tier 3 |
Permit approved on 05/01/2026, submitted on 04/23/2026. ๐ Page 10, APPROVED BY and SUBMITTED BY Recent approval date indicates active permitting cycle, with short turnaround from submission. |
2026-05-01 | General Oilfield Services |
| Tier 3 |
Anti-collision measures required, including design reductions in frac size for stages near active vertical wellbores. ๐ Page 7, Proposed Work - Operator Assertions Explicit anti-collision protocol with frac adjustments, indicating proximity to active wells and non-routine engineering to avoid interference. |
Unknown | Directional Drilling |
| Tier 3 |
Mandatory onsite inspection by NDIC Field Inspector Calob Werre prior to location construction due to aquifer location, with site-specific stipulations possible. ๐ Page 2, Stipulations - Aquifer stipulation Aquifer-specific inspection requirement adds uncertainty and potential for additional stipulations, deviating from standard permits. |
Unknown | General Oilfield Services |
| Tier 3 |
Requirement for 21-31 day written notice to adjacent operator (Proven Petroleum, well file 16840) prior to hydraulic fracturing, including emergency contacts and planned dates.โฐ TIME-SENSITIVE ๐ Page 2, Construction Commencement Notification Non-standard regulatory notice requirement for frac operations near specific adjacent wells, indicating potential interference or shared reservoir concerns not typical in all permits. |
Relative | Completions / Frac |
| Tier 3 |
Cuttings disposal designated to Roughrider Disposal LLC Landfill (SW1/4 SW1/4 Sec 10 TWP 154N RG 95W, Permit # SP-0063), subject to weather and availability changes. ๐ Page 7, Proposed Work - Disposition of Cuttings Specific landfill selection with contingencies, revealing operator's waste management strategy and potential logistical dependencies. |
Unknown | General Oilfield Services |
| Tier 3 |
Frac planned for 80 stages, 15MM lbs proppant, and 370M bbls fluid. ๐ Geologic Prognosis - WELL CONSTRUCTION DIAGRAM Detailed frac scale specification, exceeding typical permit disclosures and signaling large-scale stimulation intent. |
Unknown | Completions / Frac |