๐Ÿ›ข๏ธ Burke 418-3421H

EOG Resources, Inc. ยท Mountrail County, ND ยท File #42912 ยท Generated 2026-08-22 01:38

API
3306105687
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (5)

Tier Signal Date Service Impact
Tier 2 Production liner cemented with wet shoe for frac-out capability
๐Ÿ“„ STIPULATIONS - Conditions of Approval
West boundary setback reduced to 150' based on production liner cemented in lateral with wet shoe and ability to frac out the shoe. Non-standard completion design choice.
2026-05-07 Completions / Frac
Tier 3 Open hole log waiver approved based on offset well data
๐Ÿ“„ WELL SUNDRY FORM - DESCRIPTION (OPERATOR)
Operator successfully avoided standard open hole logging requirement by demonstrating offset well (Burke 18-27H) within one mile provides sufficient formation data. This reduces evaluation costs and time.
2026-05-08 Regulatory / Permitting
Tier 3 Closed mud system with no cuttings pit required
๐Ÿ“„ STIPULATIONS - Permit Review Policy
Non-standard environmental stipulation mandates closed-loop drilling fluid system, eliminating traditional cuttings pit.
2026-05-07 Mud / Fluids
Tier 3 Federal mineral coordination required with BLMโฐ TIME-SENSITIVE
๐Ÿ“„ Email from Doug Jackson (NDIC) to Jennifer Yu
NDIC flagged that spacing unit may be subject to Federal permit, requiring operator to contact BLM Dickinson office. Adds regulatory layer.
2026-05-06 General Oilfield Services
Tier 3 Mandatory contact with specific NDIC Field Inspector prior to location constructionโฐ TIME-SENSITIVE
๐Ÿ“„ STIPULATIONS - Construction Commencement Notification
EOG must contact NDIC Field Inspector Dylan Roach (701-770-1981) personally before starting pad construction. This creates a specific regulatory checkpoint.
Relative General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Closed-loop drilling systems
Mandatory 'Closed mud system with no cuttings pit' requirement creates immediate need for specialized fluid handling equipment and services.
Pad construction and earthwork
Detailed pad design with 28,295 CY excavation and 36,110 CY fill indicates major earthwork opportunity; construction must wait until after contact with NDIC Inspector Dylan Roach.
Cementing with frac-out capability
Production liner requires specialized cementing for wet shoe design to enable planned frac-out operation.
Filter waste management
Explicit requirement for leak-proof filter sock container on site from spud through flowback creates ongoing waste handling need.