๐Ÿ›ข๏ธ OAKLAND 154-89-33-28H-1

HUNT OIL COMPANY ยท Mountrail County, ND ยท File #42946 ยท Generated 2026-08-22 01:55

API
3306105693
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (5)

Tier Signal Date Service Impact
Tier 3 Wellbore enters Bakken Pool in Section 4 (T153N R89W) but targets spacing unit in Sections 28 & 33 (T154N R89W), requiring affidavit for off-spacing operations
๐Ÿ“„ Affidavit of Emily DiCarlo, page near end
Complex multi-section trajectory with regulatory compliance requirements for off-spacing operations
2026-04-23 General Oilfield Services
Tier 3 Anti-collision analysis shows close approaches to multiple offset wells (1.55-3.85 ft separation factors)
๐Ÿ“„ Anticollision Report section
High-density drilling environment requiring sophisticated well planning and collision avoidance
2026-04-14 Directional Drilling
Tier 3 Massive pad construction with 78,370 CY excavation and 54,135 CY embankment for 5-well pad development
๐Ÿ“„ Pad layout sections, multiple pages
Large-scale earthwork exceeding typical single-well pad requirements
2026-03-18 General Oilfield Services
Tier 3 Explicit requirement to contact NDIC Field Inspector Calob Werre (701-822-0147) prior to location construction
๐Ÿ“„ Stipulations section, page 1
Specific inspector named with direct contact requirement, not generic notification
Unknown General Oilfield Services
Tier 3 Production liner shoe fully cemented with no ability to frac out the shoe, reducing north setback to 50' (vs standard 150')
๐Ÿ“„ Stipulations section, page 1
Unusual completion design constraint that affects fracture stimulation operations and wellbore integrity planning
Unknown Completions / Frac

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Civil Construction & Earthwork
Massive pad construction (78,370 CY excavation) required before drilling; detailed designs complete with 3/18/2026 survey date
Directional Drilling & MWD Services
Complex wellpath with anti-collision requirements; Scientific Drilling already engaged for planning; precise execution needed for close-approach wells
Cementing Services
Unusual requirement for fully cemented production liner shoe with no ability to frac out; specialized cement job design needed
Environmental & Containment Services
Closed mud system, impermeable berms, filter sock containers, and cuttings hauling to approved facilities required