๐Ÿ›ข๏ธ SEVERANCE 153-89-4-9H-3

HUNT OIL COMPANY ยท Mountrail County, ND ยท File #42949 ยท Generated 2026-08-22 01:56

API
3306105696
Target Formation
Bakken
Confidence
High

๐Ÿ“Š Signals (5)

Tier Signal Date Service Impact
Tier 3 Affidavit filed stating Hunt is the operator of the offset spacing unit, therefore no inter-operator notice is required per Order 31848.
๐Ÿ“„ Affidavit of Emily DiCarlo section
Reveals the wellbore enters an adjacent spacing unit but Hunt controls it, avoiding a complex notification process with another operator. Shows strategic pad placement and unit control.
2026-04-23 General Oilfield Services
Tier 3 Closed mud system with no cuttings pit mandated.
๐Ÿ“„ Page 1, Stipulations section
This is a specific environmental stipulation requiring specialized waste handling equipment and procedures from the start of drilling.
Unknown Mud / Fluids
Tier 3 Production liner shoe is fully cemented with 'no ability to frac out the shoe'.
๐Ÿ“„ Page 1, Stipulations section; Page 7, PROPOSED WORK section
This is a specific, non-standard completion design constraint. It eliminates a common contingency (frac'ing out the shoe) and may influence liner hanger, cementing, and completion tool selection.
Unknown Completions / Frac
Tier 3 Waiver for logs must be requested via a separate sundry notice.
๐Ÿ“„ Page III (Geologic Information section)
Highlights a specific procedural hurdle for skipping standard logs. It's not a simple checkbox; it requires a formal, separate regulatory filing.
Unknown Regulatory / Permitting
Tier 3 Specific regulatory contact requirement: Hunt Oil must contact NDIC Field Inspector Calob Werre at 701-822-0147 prior to location construction.โฐ TIME-SENSITIVE
๐Ÿ“„ Page 1, Stipulations section
Direct, named inspector contact is mandated before pad construction begins, creating a specific regulatory gate and potential timing bottleneck.
Unknown General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Cuttings Hauling & Solid Waste Management
The 'closed mud system with no cuttings pit' stipulation creates an immediate, non-optional requirement for hauling all cuttings to an approved facility from spud.
Civil Construction & Earthwork
The detailed pad layout with 78,370 CY excavation and specific grading plans indicates major site work is imminent, contingent on the pre-construction call to Inspector Calob Werre.
Directional Drilling/Surveying
The complex anti-collision environment (multiple wells within <10 ft separation) and the pre-selection of Scientific Drilling indicates high-precision work is required; competitors are locked out for planning, but execution support may be needed.
Cementing Services
The 'fully cemented shoe' with no ability to frac out is a specific design requirement that will influence cement slurry design, job execution, and equipment selection for the production liner.