๐Ÿ›ข๏ธ PILSNER 2512-2BHN

KODA RESOURCES OPERATING, LLC ยท Divide County, ND ยท File #42955 ยท Generated 2026-08-22 02:00

API
3302301805
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (6)

Tier Signal Date Service Impact
Tier 3 Wellbore enters adjacent spacing unit requiring regulatory waiver from Order 31973
๐Ÿ“„ Letter to Todd Holweger dated March 26, 2026
Well trajectory crosses into adjacent spacing unit (Sections 1, 12, 13: ALL, T161N, R103W AND Section 36, T162N, R103W), requiring special regulatory coordination and waiver request. This indicates complex unit boundary management.
2026-03-26 Regulatory / Permitting
Tier 3 Surface Use Agreement was pending at permit submission with only verbal permissionโฐ TIME-SENSITIVE
๐Ÿ“„ Affidavit of Pending Surface Use Agreement dated March 26, 2026
Operator submitted permit with only verbal surface owner permission while formal agreement was still being negotiated. This indicates urgency to secure permit ahead of finalized surface terms.
2026-03-26 General Oilfield Services
Tier 3 Production liner cemented with wet shoe and ability to frac out the shoe
๐Ÿ“„ Stipulations and Completion Program sections
Specific cementing design with wet shoe for toe frac capability. Indicates planned stimulation through liner shoe.
Unknown Completions / Frac
Tier 3 Closed mud system with cuttings hauled to specific offsite facility (13 Mile Landfill, Williston, ND)
๐Ÿ“„ Proposed Work and Drilling Fluids Program sections
Explicit waste disposal plan using closed-loop system and named disposal facility. Non-routine commitment to specific landfill.
Unknown Mud / Fluids
Tier 3 Mandatory pre-construction contact with NDIC Field Inspector Marc Binnsโฐ TIME-SENSITIVE
๐Ÿ“„ Stipulations section
Specific inspector named with direct phone contact required prior to location construction. Indicates heightened regulatory oversight for this pad.
Relative General Oilfield Services
Tier 3 Existing Nelson 'B' 1 dry hole on pad with potential reserve pit excavation requirement
๐Ÿ“„ Stipulations section
Regulatory stipulation requires excavation and hauling of any encountered reserve pit from legacy well to approved facility. Adds environmental remediation scope to pad construction.
Unknown General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Earthwork and Pad Construction
Immediate need due to: 1) Required excavation of potential legacy reserve pit, 2) Large cut/fill quantities (85,210 cu yds), 3) Mandatory pre-construction inspector contact, 4) Pad built for multiple future wells.
Waste Hauling and Disposal
Locked-in requirement to haul cuttings to 13 Mile Landfill in Williston via closed-loop system. Specific facility named creates contracted opportunity.
Directional Drilling/MWD
KLX Directional pre-selected but anti-collision planning shows complex well paths with close approaches to other wells on pad. Specialized steering required.
Cementing Services
Non-routine wet shoe design with ability to frac out shoe requires precise cementing execution during liner installation.