๐Ÿ›ข๏ธ CANDY FERRARI 24-25-36 5H

Phoenix Operating LLC ยท Divide County, ND ยท File #42990 ยท Generated 2026-08-22 02:10

API
3302301820
Target Formation
Bakken
Confidence
High

๐Ÿ“Š Signals (5)

Tier Signal Date Service Impact
Tier 2 Well requires a production liner cemented in the lateral with a wet shoe and ability to frac out the shoe to justify south setback
๐Ÿ“„ Stipulations section, Conditions of Approval
Specific completion design constraint tied to regulatory approval; indicates non-standard cementing and completion approach for this well
Unknown Completions / Frac
Tier 3 Affidavit of Surface Damage Agreement executed for off-spacing wells from surface location in Section 13
๐Ÿ“„ Affidavit section, dated April 9, 2026
Surface use agreement specifically for off-spacing wells from this pad location, executed with landowner
2026-04-09 General Oilfield Services
Tier 3 Backbuild Order Waiver request submitted for traversing adjacent spacing units
๐Ÿ“„ Letter to NDIC dated February 5, 2026
Formal waiver request for drilling through adjacent spacing units with commitment to provide drilling plans
2026-02-05 Regulatory / Permitting
Tier 3 Operator must contact NDIC Field Inspector Robert Stafford prior to location constructionโฐ TIME-SENSITIVE
๐Ÿ“„ Stipulations section, Permit Review Policy
Specific inspector named with direct contact requirement before construction begins
Relative General Oilfield Services
Tier 3 Must be drilled in conjunction with a well that meets 1220' setback from east/west spacing unit boundaries to justify spacing unit
๐Ÿ“„ Page 2, spacing unit condition
Drilling of this well is contingent on another well meeting specific boundary setbacks; indicates pad coordination requirement
Relative General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Directional Drilling & Surveying
Complex multi-well pad with spacing unit crossings requires precise directional planning; Taktikal Directional already engaged but execution contractors needed
Specialized Cementing & Completions
Regulatory-mandated wet shoe liner cementing with ability to frac out shoe creates specific technical requirement for completion services
Pad Construction & Earthwork
Approved pad design with 14.8 acres disturbance and 82,380 cubic yards of earthwork; construction must wait for inspector contact
Waste Management
Closed mud system with cuttings disposal to Smoky Butte Environmental; filter sock container requirement creates ongoing waste handling needs