โ† Back to Daily Permits

๐Ÿ›ข๏ธ AJ 30-31-6-7 2H

Phoenix Operating LLC ยท Divide County, ND ยท File #43013 ยท Generated 2026-08-22 02:18

API
3302301824
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (5)

Tier Signal Date Service Impact
Tier 2 South setback approval based on production liner cemented in lateral with wet shoe and ability to frac out the shoe
๐Ÿ“„ Page 1 of 10, Stipulations
Non-standard setback approval tied to specific completion technique (wet shoe with frac-out capability)
Unknown Completions / Frac
Tier 3 Operator must provide directional drilling and completion plans to Continental Resources, Inc. for wells entering adjacent spacing unit per NDIC Orders 31848 & 31973โฐ TIME-SENSITIVE
๐Ÿ“„ Affidavit section, Meaghan Coughlan statement
Regulatory requirement for cross-unit coordination with specific competitor; creates information sharing obligation
2026-04-13 Directional Drilling
Tier 3 Anti-collision mitigation plan includes 30' surveys during build/drop/curve sections near existing dry well A. CVANCARA 9-7H
๐Ÿ“„ Letter to Todd Holweger, Anti-Collision section
Specific survey frequency increase (beyond standard) for collision avoidance; named offset well creates risk management requirement
2026-04-13 Directional Drilling
Tier 3 Well requires drilling in conjunction with another well to justify 2560-acre spacing unit - must meet 1220' setback from east/west boundaries
๐Ÿ“„ Page 2 of 10, Conditions of Approval
Creates interdependency between wells; operator must coordinate drilling of multiple wells to satisfy regulatory spacing requirements
Relative General Oilfield Services
Tier 3 Mandatory contact with NDIC Field Inspector Robert Stafford prior to location construction
๐Ÿ“„ Page 1 of 10, Stipulations
Specific inspector named with direct contact requirement; creates regulatory gate before construction
Unknown General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Directional Drilling & Surveying
Enhanced survey frequency (30' in curves) required for anti-collision; Taktikal Directional already engaged but may need additional equipment/support
Waste Management & Disposal
Closed mud system with cuttings hauling to pre-selected facility (Smoky Butte Environmental); opportunity for supplemental services
Regulatory Coordination
Multiple regulatory touchpoints required: contact Field Inspector Stafford before construction, notify Continental Resources, file sundry notices within 3 days of spud
Cementing & Completion
Wet shoe design with frac-out capability required for setback approval; specialized cementing needed for production liner