โ† Back to Daily Permits

๐Ÿ›ข๏ธ Kinzel 1-32H

Murfin Drilling Company, Inc. ยท Dunn County, ND ยท File #43019 ยท Generated 2026-08-22 02:21

API
3302505204
Target Formation
Bakken
Confidence
High

๐Ÿ“Š Signals (6)

Tier Signal Date Service Impact
Tier 2 Production liner cemented in lateral with wet shoe and no ability to frac out the shoe
๐Ÿ“„ Stipulations section and Wellbore Schematic note
Non-standard completion design limits stimulation options at shoe, affecting frac design and requiring precise stage planning
Unknown Completions / Frac
Tier 3 Wellbore enters Bakken Petroleum System outside target spacing unit, requiring waiver of Order 31973 drillback notification
๐Ÿ“„ Waiver letter to Drillback 31973
Indicates complex pad development with wellbores traversing adjacent units, requiring regulatory waiver and showing operator's multi-unit development strategy
2026-05-29 Completions / Frac
Tier 3 Closed mud system with no cuttings pit, cuttings hauled to state-approved disposal facility
๐Ÿ“„ Stipulations and Proposed Work sections
Environmental control requirement exceeds basic standards, indicating sensitive location or operator protocol
Unknown Mud / Fluids
Tier 3 Mandatory contact with NDIC Field Inspector Nicole Ewoniuk prior to location constructionโฐ TIME-SENSITIVE
๐Ÿ“„ Stipulations section
Personalized regulatory oversight requirement suggests site-specific environmental or geological concerns
Relative General Oilfield Services
Tier 3 Operator asserts no diesel-based compounds will be used in hydraulic stimulation
๐Ÿ“„ Proposed Work section
Voluntary restriction beyond regulatory requirements, indicates specific fluid chemistry preferences
Unknown Completions / Frac
Tier 3 Pad includes future SWD well in addition to three Bakken horizontals
๐Ÿ“„ Proposed Work section
Integrated disposal planning shows long-term pad strategy and water management approach
Unknown General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Directional Drilling Services
Complex trajectory with nudge section, build section, and lateral crossing unit boundaries requires precise execution; surveys required every 100ft vertical, 30ft curve, 90ft lateral
Cementing Services
Specialized cement design for production liner with wet shoe configuration; liner cemented in lateral with specific slurry designs for each casing string
Waste Hauling and Disposal
Closed mud system requires cuttings hauling to approved facility; filter sock container maintenance mandated from spud through flowback
Pad Construction and Earthwork
14,557 CY cut and 13,246 CY fill quantities specified; berm and ditch construction detailed; must contact NDIC inspector before starting
Frac Fluid and Chemical Supply
Explicit prohibition of diesel-based compounds creates opportunity for alternative fluid systems; detailed mud program with specific properties required