๐Ÿ›ข๏ธ MHA GRAIN 4892 21-19 6B

ENERPLUS RESOURCES USA CORPORATION ยท Dunn County, ND ยท File #43054 ยท Generated 2026-08-24 04:46

API
3302505213
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (8)

Tier Signal Date Service Impact
Tier 2 Approval conditional on 500' north/south and 150' east/west setbacks within 2560-acre spacing unit, with east setback based on production liner cemented in lateral with wet shoe and ability to frac out the shoe.
๐Ÿ“„ Stipulations section, Permit Review Policy
Specific setback requirements tied to a unique wellbore construction (wet shoe) that enables fracing out the shoe, indicating a tailored completion design that influences pad layout and fracture planning.
Unknown Completions / Frac
Tier 2 Wet shoe configuration detailed: uncemented annulus around toe portion of liner, allowing pump-down of first stage perforating guns on wireline.
๐Ÿ“„ Details of Standard Wet Shoe section
Specific completion technique selected to reduce cost vs. tubing or tractor perforating, indicating operator preference for efficient toe initiation.
Unknown Completions / Frac
Tier 3 Bureau of Indian Affairs approved amendment to right-of-way (FBOG101061) adding five well bores with no additional surface disturbance, effective June 16, 2026.โฐ TIME-SENSITIVE
๐Ÿ“„ Amendment #1, Approval Date: 06/16/2026
Federal right-of-way amendment approved for additional wells on existing pad without new disturbance, enabling pad densification under existing footprint.
2026-06-16 Drilling Rigs
Tier 3 NDIC Petroleum Engineer Nathaniel Erbele notified operator on March 3, 2026, that permit may be subject to Federal permit via BLM, requiring contact with BLM Dickinson office.โฐ TIME-SENSITIVE
๐Ÿ“„ Email dated 3/3/2026 8:28 AM
Federal overlay on state permit introduces additional regulatory layer and potential delay; explicit directive to engage BLM.
2026-03-03 General Oilfield Services
Tier 3 Operator requested waiver of adjacent operator notification for drilling from surface location outside spacing unit, citing self-ownership of adjacent unit.
๐Ÿ“„ Letter dated Tuesday, November 4, 2025
Operator leveraging its own adjacent unit ownership to streamline regulatory notification, demonstrating integrated asset control and efficiency in multi-well pad development.
2025-11-04 Regulatory / Permitting
Tier 3 Anticollision report dated October 16, 2025, shows multiple nearby wells with separation factors as low as 0.528 (Level 3 warning).
๐Ÿ“„ Anticollision Report, 16 October, 2025
High-density drilling environment with close approaches to existing wells, necessitating precise directional control and real-time monitoring.
2025-10-16 Directional Drilling
Tier 3 Enerplus must contact NDIC Field Inspector Clark Schackelford at 701-495-2034 prior to location construction.โฐ TIME-SENSITIVE
๐Ÿ“„ Stipulations section, Permit Review Policy
Direct, named inspector contact required before construction begins, indicating heightened regulatory oversight or specific site conditions.
Unknown General Oilfield Services
Tier 3 If pad is expanded, Enerplus must receive additional approval from Dunn County for section line encroachment pursuant to NDCC 24-06-28.
๐Ÿ“„ Stipulations section, Permit Review Policy
Explicit county-level approval required for any pad expansion, indicating regulatory scrutiny and potential for future pad modifications.
Unknown General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Directional Drilling / MWD/LWD
Anticollision report shows tight well spacing with Level 3 warnings; high-precision drilling and real-time survey monitoring are critical to avoid collisions.
Wireline & Perforating
Wet shoe configuration specifically designed for pump-down wireline perforating; service providers must be ready for toe initiation operations post-cementing.
Regulatory & Land Services
Multiple regulatory layers (BLM, BIA, county) require coordination; pending federal permit review and right-of-way amendment create time-sensitive opportunities.
Cementing
Wet shoe design requires precise over-displacement and cement top management; centralizer program detailed with specific placement across salt zones.