๐Ÿ›ข๏ธ Clearwater 44-3007H

EOG Resources, Inc. ยท Mountrail County, ND ยท File #43065 ยท Generated 2026-08-22 02:36

API
3306105704
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (7)

Tier Signal Date Service Impact
Tier 2 Production liner cemented in lateral with wet shoe and frac-out request
๐Ÿ“„ Page 2 of 10, Stipulations section and Drilling Plan cementing notes
North setback approval is conditional on a production liner cemented in the lateral with a wet shoe and 'ability to frac out the shoe.' EOG explicitly requests permission to frac out the toe. This indicates a specific completion design choice (cemented liner vs. uncemented) with planned shoe fracture.
2026-06-25 Completions / Frac
Tier 3 Cores and samples must be submitted to State Geologist with strict timelinesโฐ TIME-SENSITIVE
๐Ÿ“„ Letter dated 2026-06-26
Regulatory directive: cuttings samples within 30 days of drilling completion; any cores within 180 days. Specific collection intervals defined (30' vertical, 200' lateral). This is a post-drilling compliance activity with firm deadlines.
2026-06-26 General Oilfield Services
Tier 3 Explicit waiver required for not running porosity and resistivity logs
๐Ÿ“„ Page 9 of 10, Operator Assertions
Operator understands they must run porosity and resistivity logs unless otherwise approved by the Director. A waiver must be requested via a separate sundry notice. This highlights a regulatory requirement with a formal waiver process, not an optional item.
2026-06-25 Regulatory / Permitting
Tier 3 Specific NDIC Field Inspector contact required prior to commencing operationsโฐ TIME-SENSITIVE
๐Ÿ“„ Page 2 of 10, Stipulations section
EOG must contact NDIC Field Inspector Dylan Roach at 701-770-1981 before starting work. This creates a mandatory pre-spud checkpoint with a specific individual, not just generic notification.
2026-06-25 General Oilfield Services
Tier 3 Affidavit confirms executed surface use agreement for off-spacing facilities
๐Ÿ“„ Affidavit dated 2026-06-04
EOG filed an affidavit affirming they have an executed Access and Damage Settlement Agreement with surface owners (Meyer D. & Diane J. Kinnoin) authorizing off-spacing unit facilities placement. This resolves a potential regulatory hurdle for pad layout.
2026-06-04 General Oilfield Services
Tier 3 Multi-well pad with significant earthwork and expanded disturbance
๐Ÿ“„ Pad construction plat details (multiple pages)
Well is part of a 6-well pad (CLEARWATER 31 NENE 2). Pad expansion from 3.69 to 16.50 acres. Massive earthwork: 57,500 CY cut, 39,865 CY fill (plus 30% shrinkage). Requires compaction testing. This is a major site construction project, not a simple location.
2026-04-27 General Oilfield Services
Tier 3 Filter sock leak-proof container required on-site from spud through flowback
๐Ÿ“„ Page 9 of 10, Operator Assertions and attached memo dated May 30, 2025
Explicit reference to a 2014 rule requiring a covered, leak-proof, placarded container for filter sock disposal on-site from spud through clean-out, completion, and flowback whenever filtration is used. A waiver requires a Sundry Notice.
2025-05-30 Regulatory / Permitting

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Earthmoving, Grading & Pad Construction
Pad construction is a prerequisite. With 57,500 CY of cut and 39,865 CY of fill (plus shrinkage), this is a major immediate opportunity. Compaction testing is specified.
Cementing (Liner) & Associated Tools
The approved well design mandates a cemented production liner with a wet shoe. This requires specialized liner hanger/pack-off assembly, cementing services (Halliburton products specified), and shoe equipment for subsequent frac-out.
Directional Drilling / MWD Services
The plan specifies survey tool (Superior MWD+IFR1+SAG+F), detailed directional plan with ~21,000 ft lateral, and strict survey frequency requirements. Drilling is imminent upon permit approval (starting date: 'Upon Approval').
Waste Management / Filter Sock Containment
Regulatory requirement for a leak-proof container on-site from spud through flowback. This is a need for the entire drilling and completion duration.
Sample Collection & Shipping
Mandatory cuttings collection and potential core handling with 30/180-day clocks starting after drilling completion. Service window is defined but follows drilling.