๐Ÿ›ข๏ธ BW-Chad Allen-149-100-2826H-3

Hess Bakken Investments II, LLC ยท McKenzie County, ND ยท File #43068 ยท Generated 2026-08-22 02:37

API
3305310836
Target Formation
Bakken (Middle Bakken)
Confidence
High

๐Ÿ“Š Signals (10)

Tier Signal Date Service Impact
Tier 2 Approval conditional on 500' north/south and 150' east/west setbacks within 1920-acre spacing unit, with east setback based on production liner cemented in lateral with wet shoe and ability to frac out shoe.
๐Ÿ“„ Permit Information / Stipulations
Specific setback conditions tied to completion design (wet shoe) and ability to frac out shoe, indicating a tailored regulatory approval with operational constraints.
2026-06-25 Completions / Frac
Tier 2 Cemented liner with wet shoe design to intentionally over-displace cement by 2 bbls, with first stage pumped out shoe and subsequent stages using plug and perf.
๐Ÿ“„ Completion Equipment / Drilling Prognosis
Specific completion design detail: wet shoe with rupture pins and plug chamber for visible bump, enabling 'frac out shoe' capability as per stipulation.
Unknown Completions / Frac
Tier 3 Notification letter sent to Kent and Anita Pedersen (occupied dwelling within 1320') on June 16, 2026, as required by NDCC 38-08.05.โฐ TIME-SENSITIVE
๐Ÿ“„ Notification Letter to Surface Owners
Formal regulatory notification executed close to permit date, indicating recent engagement with nearby residents and potential for last-minute objections.
2026-06-16 General Oilfield Services
Tier 3 Affidavit provided waiving adjacent unit notification requirements because Hess is operator of adjacent unit (BW-Helga Stenseth spacing unit).
๐Ÿ“„ Letter to NDIC from Derek Abrahamsen (Hess)
Operator leveraging control of adjacent unit to streamline regulatory process, indicating pad development strategy and unit consolidation.
2026-06-09 General Oilfield Services
Tier 3 Anticollision report shows Level 3 (Closest Approach) and Level 2 (Separation Factor) warnings with offset wells (e.g., BW-Chad Allen-2826H-2, H-4, H-5, LN-H1) on same pad.
๐Ÿ“„ Anticollision Report
High-density pad drilling with close wellbore proximity; requires precise directional control and real-time monitoring.
2026-06-04 Directional Drilling
Tier 3 Surface Use Agreement and Affidavit executed with surface owners (Barbara Olson & Sharen Nelson Revoc. Trust) effective December 1, 2025, for pad construction.
๐Ÿ“„ Affidavit of Well Pad Location and Surface Use Agreement
Surface access secured well in advance (6+ months before permit date), showing proactive land management and reduced surface risk.
2025-12-01 General Oilfield Services
Tier 3 Closed mud system with no cuttings pit required.
๐Ÿ“„ Conditions of Approval
Non-standard waste handling mandate; eliminates traditional cuttings pit, requiring alternative disposal (hauling to approved facility).
Unknown Mud / Fluids
Tier 3 Operator must contact NDIC Field Inspector Will Ryan (701-770-6684) prior to location construction.
๐Ÿ“„ Conditions of Approval
Explicit pre-construction contact requirement with a named inspector, indicating heightened regulatory oversight or site-specific sensitivities.
Unknown General Oilfield Services
Tier 3 Perimeter berm required surrounding entire location.
๐Ÿ“„ Conditions of Approval
Specific containment requirement beyond typical pad design; indicates environmental or runoff control concerns.
Unknown General Oilfield Services
Tier 3 Environmental studies for pad location to be completed Spring 2026 (noted on grading plan).โฐ TIME-SENSITIVE
๐Ÿ“„ Well/Facilities Pad Grading Plan Note
Environmental studies pending as of plan date (early 2026), representing a potential pre-construction contingency.
Relative General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Civil Construction & Earthwork
Pad grading plans are finalized (early 2026); construction imminent pending environmental studies and inspector contact. Perimeter berm, closed mud system, and specific compaction requirements create specialized scope.
Directional Drilling & MWD
Anticollision warnings (Level 2/3) indicate need for high-precision drilling and real-time surveying; pad has multiple close-proximity wells requiring expert navigation.
Cementing & Completion Services
Specific wet shoe liner design required; cementing program includes detailed centralizer placement and slurry designs for production casing and liner.
Waste Hauling & Disposal
Closed mud system with no cuttings pit mandates hauling cuttings to approved facility; explicit requirement creates immediate demand.
Environmental Consulting
Environmental studies noted for Spring 2026 completion; likely needed before construction can proceed.