๐Ÿ›ข๏ธ BRENDA 2 SWD

Phoenix Operating LLC ยท McKenzie County, ND ยท File #43112 ยท Generated 2026-08-22 02:53

API
3305310840
Target Formation
Inyan Kara Formation (Dakota Group)
Confidence
High

๐Ÿ“Š Signals (6)

Tier Signal Date Service Impact
Tier 3 Permit expiration deadline: well must be completed as Saltwater Injection well by July 13, 2027, or permit expiresโฐ TIME-SENSITIVE
๐Ÿ“„ Page 3 of 10, UIC stipulations
Creatures a hard deadline for completion and injection operations, driving urgency in construction and commissioning timeline
2027-07-13 General Oilfield Services
Tier 3 Requirement to submit detailed facility schematic and construction dates within 30 days of construction completionโฐ TIME-SENSITIVE
๐Ÿ“„ Page 2 of 10, UIC stipulations
Creates a defined post-construction documentation window with specific content requirements
Relative General Oilfield Services
Tier 3 Pressure test required on high-pressure injection pipeline (100 psi over permitted max) prior to injection, with detailed reporting
๐Ÿ“„ Page 2 of 10, UIC stipulations
Specific testing protocol exceeds routine pressure testing requirements
Relative General Oilfield Services
Tier 3 SWD facilities co-located with planned oil production facilities within same berms
๐Ÿ“„ UIC Plan section 7
Unknown General Oilfield Services
Tier 3 Tank diking variance approved contingent on submission of as-built schematic after construction
๐Ÿ“„ Page 3 of 10, UIC stipulations
Regulatory flexibility granted but requires post-construction documentation, indicating non-standard facility design
Relative General Oilfield Services
Tier 3 No plans to take third-party volumes at this time
๐Ÿ“„ UIC Plan section 6
Explicit statement limiting disposal to operator's own production, indicating captive use strategy
Unknown General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Pressure Testing Services
Required 100 psi over-pressure test on injection pipeline before injection can begin; must be timed with facility completion
Surveying & As-Built Documentation
Tank diking variance requires as-built schematic submission after construction; 30-day window for facility schematic submission
Pipeline Construction & Boring
329' bore required for Swenson to Brenda flowline; detailed pipeline plan already engineered
SCADA & Monitoring Systems
Operator committed to 24-hour SCADA with specific alarms; integration needed with facility construction