Phoenix Operating LLC ยท McKenzie County, ND ยท File #43117 ยท Generated 2026-08-22 02:58

API
3305310841
Target Formation
Inyan Kara Formation (Dakota Group)
Confidence
High

๐Ÿ“Š Signals (6)

Tier Signal Date Service Impact
Tier 3 Permit includes a tank diking variance request approved contingent on submission of as-built schematic after construction.
๐Ÿ“„ Page 3 of 11, UIC Stipulations
Regulatory flexibility granted for facility design, indicating potential non-standard tank dike dimensions. Requires post-construction compliance submission.
2026-07-13 General Oilfield Services
Tier 3 Approach permit (AP2026-028) submitted and awaiting approval as of application date; installation date targeted for 2026-06-01.โฐ TIME-SENSITIVE
๐Ÿ“„ Appendix F: Approach Permit Application
Access road construction is pending county approval, indicating a near-term construction start window. Contractor (Trotter Construction INC) is pre-selected.
2026-06-01 General Oilfield Services
Tier 3 Operator plans to only inject water from on-pad wells (LOGAN FED 4-9-16 1HF through 4HF), not third-party volumes at this time.
๐Ÿ“„ UIC Plan, Section 6: Proposed Injection Program; Appendix D
Dedicated disposal for a specific 4-well pad cluster, not a commercial SWD open to external sources. Indicates a closed-loop system for Phoenix's own production.
Unknown Mud / Fluids
Tier 3 SPCC Plan must be implemented within six months of facility commissioning.โฐ TIME-SENSITIVE
๐Ÿ“„ UIC Plan, Section 8: Spill Prevention and Monitoring Controls
Regulatory deadline tied to operational start, not permit date. Requires specific planning and documentation post-construction.
Relative General Oilfield Services
Tier 3 SWD facilities and oil production facilities are co-located within the same berms on the pad.
๐Ÿ“„ UIC Plan, Section 7: Facilities Design
Integrated facility design reduces surface footprint but increases complexity of containment, monitoring, and spill prevention. Shared infrastructure implies coordinated construction and operations.
Unknown General Oilfield Services
Tier 3 Drill cuttings to be hauled to a licensed disposal facility: Select Water Solutions, LLC at 13195 26th St NW Arnegard, ND.
๐Ÿ“„ Well Pad Design, Section 4: Drilling Fluids and Cuttings Program
Explicitly names a waste disposal vendor and location, indicating a pre-arranged contract for drilling waste.
Unknown General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Civil Construction & Earthwork
Approach permit pending approval with targeted June 2026 start. Pad construction (berms, grading, liner installation) must follow immediately to meet SWD facility construction deadlines.
SCADA & Automation Systems
Facility design mandates remote monitoring, alarms, and ESDVs. Integration required for co-located SWD and production facilities. Must be commissioned before injection begins.
Environmental Compliance & Planning
SPCC plan required within 6 months of commissioning. As-built schematics and sundry notices due within 30 days of construction completion. Regulatory reporting timelines are triggered by construction milestones.
Pressure Testing & Pipeline Services
Stipulation requires 100 psi over-pressure test on injection pipeline prior to injection, with detailed reporting. Service needed between pump installation and operational start.