๐Ÿ›ข๏ธ Sloane 25-24-13 3HF

Rockport Energy Solutions LLC ยท McKenzie County, ND ยท File #43147 ยท Generated 2026-08-22 03:10

API
3305310853
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (7)

Tier Signal Date Service Impact
Tier 3 Federal mineral review triggered - BLM coordination requiredโฐ TIME-SENSITIVE
๐Ÿ“„ Email from Nathaniel Erbele (NDIC) dated 2026-07-23
Permit flagged for federal mineral involvement. Requires additional BLM documentation, adding regulatory step.
2026-07-23 Drilling Rigs
Tier 3 Drill-back notification waiver provided to offset operator (Chord Energy)
๐Ÿ“„ Waiver โ€“ Drill Back Offset Operator Notification
Formal notification already completed with adjacent operator, including detailed technical plans. Shows proactive regulatory compliance.
2026-07-23 Regulatory / Permitting
Tier 3 Off-spacing well requiring surface use agreement with landowner
๐Ÿ“„ Affidavit Affirming Surface Use Agreement
Well is off-unit (surface location not aligned with spacing unit). Agreement already executed and notarized, showing advanced land work completed.
2026-07-07 General Oilfield Services
Tier 3 Specific directional drilling vendor (Taktical Directional) used for detailed well planning
๐Ÿ“„ Directional Plan section, Taktical Directional header
Vendor explicitly named in detailed directional plan with specific proposal (#3). Shows operator's established relationship and technical reliance.
2026-06-16 Directional Drilling
Tier 3 Rig contract signed with Patterson 290 for 4-well padโฐ TIME-SENSITIVE
๐Ÿ“„ Page 7 of 10, Proposed Work section
Operator has already secured rig contractor before permit approval, indicating firm commitment and advanced planning. Patterson 290 is specifically named.
Relative Drilling Rigs
Tier 3 Waiver requested for open hole logs (porosity/resistivity)
๐Ÿ“„ Page 4 of 10, Proposed Logs section; Page 10 of 10, operator assertions
Operator is opting out of standard logging requirements, indicating cost-saving intent and confidence in geologic model. Requires separate sundry notice.
Unknown Regulatory / Permitting
Tier 3 Specific liner hanger/packer system (Innovex 7" x 5") specified in casing program
๐Ÿ“„ Well Program & Schematic section
Exact equipment brand and model specified in drilling prognosis, indicating pre-selected vendor or strict engineering requirement.
Unknown General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Pad construction and earthwork
Location construction planned to start 10/01/2026 upon permit approval. Detailed earthwork quantities (24,380 cu yds cut) and pad design already completed by UELS. Immediate need for grading, berm construction, drainage.
Cementing services
Detailed cement program specified with exact volumes, densities, additives. Surface casing requires 60% excess cement, production casing requires specific lead/tail design. Must align with rig schedule starting ~11/1/2026.
Mud engineering and fluids
Specific mud program detailed: fresh water to 2313', OBM 9.8-10.3 ppg to 11651', brine 9.6-10.2 ppg in lateral. Closed mud system required by permit. Services needed for ~11/1 spud.
Frac and completion services
Detailed completion procedure specifies wireline plug and perf, 15K wellhead equipment, casing test to 11,500 psi. Stimulation plan explicitly excludes diesel-based compounds. Services needed after drilling completion.
Environmental and waste management
Closed mud system required, dry cuttings hauled to approved facility, filter sock container mandated from spud through flowback. Immediate need for waste handling equipment and services.