๐Ÿ›ข๏ธ Sloane 25-24-13 4HF

Rockport Energy Solutions LLC ยท McKenzie County, ND ยท File #43148 ยท Generated 2026-08-22 03:11

API
3305310854
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (5)

Tier Signal Date Service Impact
Tier 3 Operator signed rig contract with Patterson 290 with estimated spud date 11/1/2026 and location build start 10/01/2026โฐ TIME-SENSITIVE
๐Ÿ“„ Page 6 of 10, PROPOSED WORK section
Explicit rig contract and firm timeline disclosed in permit; shows advanced planning and commitment
2026-11-01 Drilling Rigs
Tier 3 North setback condition based on production liner cemented in lateral with wet shoe and ability to frac out the shoe
๐Ÿ“„ Page 2 of 10, STIPULATIONS section
Specific completion technique requirement (wet shoe system) imposed as regulatory condition for boundary setback
2026-07-23 Completions / Frac
Tier 3 Federal minerals notification required - BLM must be contacted for proper documentationโฐ TIME-SENSITIVE
๐Ÿ“„ Email from Nathaniel Erbele dated 7/23/2026
Additional federal regulatory layer identified after permit approval; creates potential delay vector
2026-07-23 General Oilfield Services
Tier 3 Operator must drill this well in conjunction with another well that meets a 1220' setback from east/west boundaries to justify the spacing unit
๐Ÿ“„ Page 3 of 10, WELL INFORMATION section
Creates interdependency between wells on pad; forces coordinated drilling schedule and potentially affects pad sequencing
2026-07-23 General Oilfield Services
Tier 3 Dry cuttings from this well will be hauled to State approved disposal facility (not standard closed mud system only)
๐Ÿ“„ Drilling Prognosis section, Note after Summary Drilling Procedure
Explicit waste handling method specified beyond standard closed mud system requirement
Unknown Mud / Fluids

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Pad construction and earthwork
Location build scheduled to start 10/01/2026; detailed earthwork quantities (24,380 Cu. Yds cut) and pad design already completed
Specialized cementing and liner services
Wet shoe system required by permit; specific cement additives and centralizer placement detailed in drilling prognosis
Waste handling and disposal
Explicit requirement to haul dry cuttings to approved facility; filter sock container mandate with specific compliance requirements
BLM/federal regulatory coordination
Federal minerals notification required immediately post-permit; potential schedule impact if not addressed promptly