๐Ÿ›ข๏ธ MONKEY BARREL 14-23-26-35 5H

Phoenix Operating LLC ยท Divide County, ND ยท File #43193 ยท Generated 2026-08-22 03:22

API
3302301855
Target Formation
Bakken
Confidence
High

๐Ÿ“Š Signals (5)

Tier Signal Date Service Impact
Tier 2 South setback based on production liner cemented in lateral with wet shoe and ability to frac out the shoe
๐Ÿ“„ Stipulations section, page 2
Specific engineering requirement for completion design with wet shoe technology
Unknown Completions / Frac
Tier 3 Permits suspended due to revocation request by Koda Resources Operating, LLC; hearing scheduled for September 2026 docketโฐ TIME-SENSITIVE
๐Ÿ“„ Letter from NDIC dated August 13, 2026
Unusual regulatory action where competitor is actively seeking to revoke permits, creating uncertainty and potential delay
2026-08-13 General Oilfield Services
Tier 3 Operator required to notify adjacent spacing unit operator (Formentera Operations, LLC) with detailed drilling and completion plans per NDIC Order 31848
๐Ÿ“„ Affidavit section, page near end
Regulatory requirement for cross-unit coordination with specific competitor
2026-08-06 General Oilfield Services
Tier 3 Must contact NDIC Field Inspector Marc Binns prior to location constructionโฐ TIME-SENSITIVE
๐Ÿ“„ Conditions of Approval, page 2
Specific inspector named for pre-construction notification
Relative General Oilfield Services
Tier 3 Must drill Monkey Barrel 14-23-26-35 4H back-to-back with another well that complies with 1220' setback to justify spacing unit
๐Ÿ“„ Stipulations section, page 2
Unusual conditional approval requiring specific drilling sequence and spacing compliance
Relative General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Legal/Regulatory Services
Permit revocation hearing scheduled for September 2026 creates immediate need for regulatory representation and hearing preparation
Drilling & Completion Services
Back-to-back drilling requirement creates sequencing opportunity; wet shoe installation and frac-out capability needed for completion
Environmental/Waste Management
Pre-selected disposal vendor indicates waste management planning is advanced; closed mud system required
Pad Construction & Earthwork
Large earthwork quantities (57,990 Cu. Yds.) with specific grading requirements; must contact inspector before construction