| Tier | Signal | Date | Service Impact |
|---|---|---|---|
| Tier 2 |
South setback based on production liner cemented in lateral with wet shoe and ability to frac out the shoe ๐ Stipulations section, page 2 Specific engineering requirement for completion design with wet shoe technology |
Unknown | Completions / Frac |
| Tier 3 |
Permits suspended due to revocation request by Koda Resources Operating, LLC; hearing scheduled for September 2026 docketโฐ TIME-SENSITIVE ๐ Letter from NDIC dated August 13, 2026 Unusual regulatory action where competitor is actively seeking to revoke permits, creating uncertainty and potential delay |
2026-08-13 | General Oilfield Services |
| Tier 3 |
Operator required to notify adjacent spacing unit operator (Formentera Operations, LLC) with detailed drilling and completion plans per NDIC Order 31848 ๐ Affidavit section, page near end Regulatory requirement for cross-unit coordination with specific competitor |
2026-08-06 | General Oilfield Services |
| Tier 3 |
Must contact NDIC Field Inspector Marc Binns prior to location constructionโฐ TIME-SENSITIVE ๐ Conditions of Approval, page 2 Specific inspector named for pre-construction notification |
Relative | General Oilfield Services |
| Tier 3 |
Must drill Monkey Barrel 14-23-26-35 4H back-to-back with another well that complies with 1220' setback to justify spacing unit ๐ Stipulations section, page 2 Unusual conditional approval requiring specific drilling sequence and spacing compliance |
Relative | General Oilfield Services |