EOG RESOURCES, INC. ยท Mountrail County, ND ยท File #43305 ยท Generated 2026-09-17 03:50

API
3306105721
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (4)

Tier Signal Date Service Impact
Tier 2 Approval condition includes a 500' south boundary setback at TD based on a production liner cemented in the lateral with a wet shoe and 'the ability to frac out the shoe.' Operator later formally 'requests permission to frac out the toe.'
๐Ÿ“„ STIPULATIONS and cementing schematic
The permit's approval is structurally dependent on a specific, non-standard completion technique (frac-ing out a cemented wet shoe), which is explicitly requested by the operator.
Unknown Completions / Frac
Tier 3 Operator requested waiver from NDIC Orders 31848 and 31973 for drilling into adjacent spacing units, citing self-ownership of all adjacent units.โฐ TIME-SENSITIVE
๐Ÿ“„ Waiver request letter
Reveals a specific regulatory strategy to bypass notification requirements, indicating a streamlined, operator-controlled development plan for the pad.
2026-08-27 Regulatory / Permitting
Tier 3 Construction commencement requires contacting NDIC Field Inspector Calob Were prior to location construction, with a specific phone number provided.
๐Ÿ“„ Construction Commencement Notification
Identifies a specific, named regulatory inspector as the mandatory point of contact for pad construction start, a non-routine procedural step.
Relative General Oilfield Services
Tier 3 Proposed work states Shell 59-3305H & Shell 60-3334H are waiting on a hearing in October 2026, but EOG wants an approved permit for this well to build pad prior to winter, with all four wells to be drilled simultaneously.โฐ TIME-SENSITIVE
๐Ÿ“„ PROPOSED WORK section
Explicitly links this well's permit approval to winter pad construction timing and reveals a batch-drilling plan for four wells, not just this single well.
Relative General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Pad Construction & Earthwork
Permit approval is explicitly needed to 'build prior to winter.' Detailed pad construction plans with cut/fill volumes exist, indicating imminent mobilization for grading and site preparation in late 2026.
Directional Drilling & MWD
A batch-drilling plan for four wells is declared to start after pad build. The well plan specifies survey tools (Superior MWD+IFR1+SAG+FI) and detailed directional plans, indicating near-term contracting needs.
Cementing & Specialized Completions
The well's approval and design are contingent on a specific cement job for a production liner with a wet shoe that must be fractured out, creating a defined, non-standard service requirement for the completion phase.